SAIB Aseel Offers
What we deliver, and when

Proposal and time to build · 28 November 2026

High level only. The proposal, designs and dates can change after deeper analysis.
Standard
~12 weeks
From greenlight to go-live. Example: greenlight 7 Dec, live end of Feb 2027
Fast-track
~8 weeks
From greenlight, as top priority. Example: live end of Jan 2027

→ next · ← back · Esc all slides · F fullscreen · N notes · D dark

The ideaHow it worksClick a step for detail

A SAIB customer gets a unique discount code and uses it at a partner

1
Opens offers in the SAIB app
Signed in through SAIB SSO
2
Picks an offer
In store or online
3
Gets a unique code
Issued by MGC
4
Redeems at the partner
Web POS in store, checkout online
5
Merchants join and publish
Merchant portal, Merit review
6
SAIB sees usage
Report by offer and outlet
Press Play, or click any step.
ProposalWhat we deliverSome parts are built together

Merit delivers seven parts; SAIB delivers the sign-in on its side and the approvals

1
Offers marketplace with SAIB sign-in
Opens from the SAIB app, no second login
2
Discount codes on MGC
Percentage off with a cap, one unique code per customer
3
Merchant portal
Join from an invite link, add outlets, create offers
4
Merit review
Merit ops approves each merchant and offer
5
Cashier web POS
Check and redeem a code on a phone or tablet
6
Online redemption
Partners apply the code at their own checkout
7
Usage report to SAIB
Codes issued and used, by offer and outlet
SAIB
SSO, SAMA No Objection, UAT sign-off
SAIB's side of the sign-in, plus the approvals

Designs are a proposal and can change after the detailed technical review.

TimelineTime to build, from greenlightToggle the version and the view

About 12 weeks from greenlight to go-live, at normal priority

View
Go-live end of Feb 2027
BuildDesign, and UAT with SAIBIndicative go-live

Indicative. Holds only with no blockers from SAIB or others (next slide). Each week the greenlight slips moves go-live by a week.

Time to buildAssumptionsIf one fails, the dates move

The build time holds only with no blockers from SAIB or anyone else

1
Greenlight
Signed contract or SOW, or a written go-ahead; team assigned from day one
2
No client blockers
SAIB builds and tests its half of SSO in parallel, gives environments and access on time, answers within two business days
3
UAT on time
SAIB starts UAT on the planned week and signs off within two weeks
4
Scope stays fixed
SAIB's own journey design (due 15 Dec) does not change the scope
5
Approvals in place
SAMA No Objection holds; no new regulatory need such as KSA data residency
6
Partners ready
Launch partners named and on the web POS or our API; no custom POS integrations
7
Current hosting
Runs on current Merit infrastructure
8
Technical review
The detailed review confirms this high-level view
9
No holidays counted
Add about one week if the team takes year-end leave
10
Fast-track only
Top priority, with a larger dedicated team
MERITProduct
Brian Arfi Faridhi

Thank you

High level, subject to change after deeper analysis.

Related: proposal document · delivery project plan

“Patience is the key to relief.”
Arabic proverb
Standard
~12 weeks
From greenlight to go-live
Fast-track
~8 weeks
From greenlight, as top priority