Rewards Portal: World 1 work list
v0.2, 26 Nov 2026 (v0.2 adds the 30 Nov to 3 Dec slip; v0.1, 20 Nov, first list). The Rewards Portal counterpart of the Al Fursan migration scope tree and the Merit App scope tree. 39 open issues in the Rewards Portal Go-Live Requirements project (World 1) plus 3 delivery tickets behind them, grouped by work area. Status, owners and priorities come from Linear (read live 20 Nov); no estimates or dates are committed anywhere yet, so the ask to Wshah, Habeeb and Fayez is to confirm the list, name missing owners, and put estimates and dates on the urgent rows. Click an issue id to open it in Linear.
Sources: Rewards Portal Go-Live Requirements project on Linear (W1 team, 39 issues, snapshot 20 Nov 2026), the World 1 delivery tracker draft (20 Nov), and the Wshah payouts overview shared 19 Nov. Dates in the October migration plan draft (freeze 20 Nov, pilot 24-27 Nov, waves done 4 Dec) are unconfirmed and are not shown as commitments.