The first sprint builds one thing: a gate on supplier rates

From 13 Oct, every supplier rate change on a gift card waits for approval before it goes live. The old rate stays live until then. Finance sees each change, up or down. Client prices do not change in this sprint. Three more builds follow, and two of them still wait on answers.

Companion material

01What the first sprint builds

3b is the supplier rate change gate. Follow one change through it. The gate protects the rate stored against the supplier, before anything reaches a client.

on proposal on live change no link in 3b CSV upload3B Manual entry3B Pending record old rate stays live previous, new, delta direction, source proposed by, proposed at Approve or reject Faras Ismail or Amr AboKhalil one approval is enough Rejectedwritten reason required Supplier rate record new rate goes live approver and time stored only the queue writes here Client pricesunchanged, still updated by hand Finance alertfires for an increase and a decrease
IntakeApproval gateLive supplier dataFinance alertNot changed in 3b

1. A supplier changes a gift card rate, for example a discount that drops from 4 percent to 1 percent. Someone uploads it in a CSV file.

What does not change in 3b

Not in 3b

Client prices

Still updated by hand, as today. Client pricing comes in Phase 2 (2a, 2b, 4d).

Not in 3b

MGC

No sync to MGC. Propagation comes in Phase 2 (2a, 2b, 4d).

Not in 3b

Margin guard

No automatic loss check. It comes in the 3b margin guard and 4a.

Not in 3b

Revenue engine

No FX, VAT or fee calculation. It comes in the 3b margin guard and 4a.

Not in 3b

Reconciliation

No variance alarm. It comes in 4c.

Not in 3b

Monthly client email

No client notice. It comes in Phase 2 (2a, 2b, 4d).

Why 3b removes the main risk. Today a supplier rate can change with no approval and no alarm. A drop from about 4 percent to 1 percent can pass silently. After 3b, no supplier rate goes live without approval. A decrease raises an alert, the same as an increase.
Gift cards only, CSV and manual only. No supplier catalogue API and no supplier portal exist for gift cards. So the gate takes CSV upload and manual entry. Merchandise is out of scope.

023b build detail

For developers. Taken from the 3b Build Brief. Akshay Chennupati confirms or changes the proposals at sprint planning on 13 Oct.

Decidedagreed on 12 Oct, or fixed in Build Spec v1.1 Proposeda proposal so that work can start Opennobody knows yet, see open items

Scope: in and out Decided

In 3bOut of 3b
Gift cards onlyMerchandise products
Supplier rate changes: discount, markup, processing feeClient price updates and client revenue-share logic (Phase 2 (2a, 2b, 4d))
Intake by CSV upload and manual entrySupplier catalogue API and supplier portal. Neither exists for gift cards
One approval queue, one approver role, written rejection reasonMargin guard, revenue engine, FX and VAT controls (3b margin guard and 4a)
Finance alerts on proposal and on live change, both directionsAccount Manager alerts and the monthly client email (Phase 2 (2a, 2b, 4d))
Full audit trail: who proposed, who decided, when, and whyReconciliation and variance alarms (4c)
No other way to change a supplier ratePropagation to client catalogues and MGC

Input validation (F6) is a maybe. Proposed Include it only if Finance gives the bounds before sprint planning on 13 Oct. If not, it moves to the 3b margin guard and 4a (open item O7).

The supplier rate record Proposed fields

Decided The approval is for the value stored against the supplier. The master product carries no discount. A discount sits on the supplier or on the client. Engineering chooses the field names.

FieldTypeNotes
Product (gift card brand)referenceExisting catalogue product
SupplierreferenceExisting supplier. One product can have four or five ranked suppliers
Rate typediscount or markupOne sign convention. The spec uses a negative rate for a supplier discount and a positive rate for a supplier markup
Rate value (percent)decimalThe new value
Processing feedecimalIf the supplier charges one
Previous valuedecimalCopied from the live record when the change is proposed
Delta and directioncalculatedNew minus previous. Direction is up, down or unchanged
SourceCSV or manualLater: API or portal, only if one exists
StatusstatePending, approved, rejected, superseded. See the states below
Proposed by, proposed atuser, timestamp
Decided by, decided atuser, timestampFilled on approve or reject
Rejection reasontextRequired when status is rejected

Not stored here: the revenue-share split (80-20, 50-50, 70-30). It belongs to the client side and arrives with Phase 2 (2a, 2b, 4d).

How a change gets in

Decided Anyone with catalogue access can propose a change: accounts, partnerships or finance. Every entry goes through the queue. The same person may propose and approve. Finance still has to accept that (open item O9).

CSV ruleDetail
Columnsproduct, supplier, rate type, rate value, processing fee (optional), note (optional) Proposed
One rowOne pending record Proposed
Row errorsA bad row is listed with its row number and reason. Good rows in the same file are still created Proposed
Same product and supplier twiceReject both rows. One pending record per product and supplier at a time Proposed
A pending record already existsThe new proposal replaces it. The old one is marked superseded Proposed

Manual entry: one form with the same fields as one CSV row. Proposed

Approval states

proposed CSV or manual approve reject + reason newer proposal written Pendingold rate stays live Approvedapprover and time Rejectedreason required Supersededsame product, supplier Livesupplier record
RuleStatus
Only the queue writes a supplier rateNo direct edit, no bypass Decided
Old rate stays live while pendingIf nobody approves, the old price stays Decided
One approver role, two peopleFaras Ismail and Amr AboKhalil. One approval is enough Decided
No escalation tierNot in 3b Decided
Rejection needs a written reasonThe system refuses an empty reason Decided
Approval stores approver and timeOn every approval Decided
Approve and reject are the only actionsNo edit in the queue. To change a value, reject and propose again Proposed

Queue screen Proposed One list. Columns: status, product, supplier, previous, new, delta, direction, source, proposed by, proposed at. Filters: status, supplier, direction. Default view: pending, oldest first. One action per row: approve, or reject with a reason.

Alerts

AlertWhenGoes toStatus
ProposedA pending record is createdFinance only, for confidentialityDecided
Live changeA change is approved and writtenFinanceDecided
Both directionsAlways. Increases and decreases both alarmFinanceDecided
ChannelEmail, in-app or Slack. Use what the platform already hasOpen O3

Account Manager alerts on revenue-share changes belong to Phase 2 (2a, 2b, 4d). Akshay asked that Finance also gets those. That is noted for Phase 2 (2a, 2b, 4d).

Acceptance criteria

Each criterion passes or fails. AC1 to AC4 come from Build Spec v1.1. AC-N1 to AC-N5 are new, from the 12 Oct meeting.

#GivenWhenThen
AC1A supplier rate arrives by CSV or manual entryIt is savedA pending record exists with delta, direction and source. The live supplier rate is unchanged. Finance receives one alert
AC2A pending changeFaras Ismail or Amr AboKhalil approves itThe supplier record shows the new value and the approver and time. A second alert fires
AC3A pending changeThe approver rejects it with no reasonThe system refuses the rejection
AC4A rate decrease, for example 4 percent to 1 percentIt is proposedAn alert fires, same as for an increase
AC-N1A pending change that nobody approvesAny time passesThe old rate is still live. No order uses the pending value
AC-N2Any user, screen or APITries to change a supplier rate without the queueThe system refuses
AC-N3A CSV with 10 rows, 2 invalidIt is uploaded8 pending records exist. The 2 invalid rows are listed with row numbers and reasons
AC-N4The same user proposes and approvesThe change is approvedThe system allows it. The record shows the same user on both lines
AC-N5A user who is not Faras Ismail or Amr AboKhalilTries to approveThe system refuses
AC7Only if validation is in. A discount or fee outside its boundsIt is submittedThe change is blocked before it reaches an approver

Questions only the tech team can answer

These change the size, not the scope. Akshay answers them at sprint planning on 13 Oct.

#QuestionWhy it matters
T-Q1Where does the supplier rate live today, and what writes to it?Decides where the queue and the record sit (T1)
T-Q2Is there a CSV upload tool for the catalogue?Extend it, or build it new
T-Q3Which alert mechanism exists on the platform?Decides O3
T-Q4Can an existing role or permission model carry the approver role?Decides how "Faras Ismail or Amr AboKhalil only" is enforced
T-Q5Does an existing computation already apply fee components to a client transaction?Not for 3b. It decides if the 4a revenue engine is new or a change

Definition of done

  1. AC1 to AC4 and AC-N1 to AC-N5 pass in staging, with Finance present for the walkthrough.
  2. No screen or API writes a supplier rate outside the queue.
  3. Finance receives both alerts, for an increase and for a decrease.
  4. Faras Ismail or Amr AboKhalil approves and rejects a real sample file of gift card rates.
  5. Manual processing of client prices continues in parallel. Nothing in 3b changes a client price.

03Build order, then KSA go-live

Only 3b is committed. The rest wait on open answers. Manual processing continues in parallel until KSA go-live. Dates assume two-week sprints from 13 Oct.

13 OCT NOV DEC JAN FEB 3b Approval workflow, supplier rate gate: 13 to 26 Oct. Committed in principle 3b · gate13-26 OctCOMMITTED 3b margin guard and 4a revenue engine: 27 Oct to 9 Nov. Not committed, waits on O5 and O7 3b/4a · engine27 Oct-9 NovNOT COMMITTED Phase 2 (2a, 2b, 4d), client pricing and propagation: 10 to 23 Nov. Blocked by O1, O2, O4, O6 2a/2b/4d · clients10-23 NovBLOCKED 4c Reconciliation and month-end data: 24 Nov to 7 Dec. Details not yet written 4c · month-end24 Nov-7 DecNOT WRITTEN KSA go-live, around 20 customers. A target. It moves if Phase 2 (2a, 2b, 4d) moves KSA go-live~20 customersTARGET, CAN MOVE UAE, January, once the KSA close is clean UAEJanuary UK, February, about one month after UAE UKFebruary Build: 4 steps x 2-week sprints Rollout by entity, about one month apart
3b · 13 to 26 OctCommitted in principle

Approval gate for supplier rates

Ships
Every supplier rate change (discount, markup, processing fee) by CSV or manual entry becomes a pending record. The old rate stays live. Faras Ismail or Amr AboKhalil approves, or rejects with a reason. Finance gets an alert both ways.
Finance uses
One queue with every proposed supplier change, its delta, direction and source, before it goes live. Client prices are still updated by hand.
Builds
F1 intake (CSV, manual) · F2 no bypass, on the supplier rate record · F8 approval queue · F9 Finance alerts · F6 bounds only if O7 is answered
Accepted when
AC1 to AC4, AC-N1 to AC-N5 (AC7 if validation is in)
Open
Sizing. Alert channel (O3). Validation bounds (O7).
3b margin guard and 4a · 27 Oct to 9 NovNot committed, waits on O5, O7

Margin guard and revenue engine

Ships
The margin guard flags a change when a fixed client discount meets or exceeds the live supplier margin. It runs at setting only. The engine calculates FX, VAT on margin and fees. The order-date rate is stored on the transaction. Input validation, if it is not in 3b.
Finance uses
Loss-making changes flagged before they go live. A later rate change never re-prices a placed order.
Builds
F3 revenue engine · F5 margin guard · F12 markup as processing fee · F6 if moved
Waits on
O5: a new engine, or a change to the existing computation. O7: validation bounds.
Phase 2 (2a, 2b, 4d) · 10 to 23 NovBlocked, O1, O2, O4, O6

Client pricing and propagation

Ships
One pricing conditional. A revenue-share field and lookup. Approved changes reach client catalogues and MGC. One monthly email per client.
Blocked by
May Merit change a fixed-margin client price without client approval (O1)? What happens on a supplier switch (O2)? Does the system hold revenue-share values per client (O4)? How does 30-day notice fit on-time updates (O6)?
Next answer
The accounts team answers on Tue 13 Oct, 17:00 GST.
Builds
F4 revenue share · F10 propagation · F11 pricing conditional · F13 monthly client email · F9 Account Manager alerts
4c · 24 Nov to 7 DecDetails not yet written

Month-end data and reconciliation

Ships
Claim status against the month-end cutoff. An expiry date on each card from its brand term. A variance alarm when booked revenue differs from expected revenue.
Builds
Build Spec section 7 month-end data · F7 reconciliation
Waits on
The source of the expiry term per brand (Finance item 2).
Target · December closeThen UAE, UK

KSA go-live, around 20 customers

This is a target, not a commitment. It moves if Phase 2 (2a, 2b, 4d) moves. Manual processing runs in parallel for one month-end close. UAE follows in January and UK in February, about one month apart, once the KSA close is clean.

04What changed after the 12 Oct review

The tech team asked what exactly the first sprint builds. Plan v0.1 could not answer. The review also showed parts of v0.1 were wrong or missing.

#v0.1 saidThe meeting showedEffect
1The gate protects the Master Online CatalogueA master product carries no discount. The discount sits on the supplier or on the clientThe gate protects the supplier rate record
23b margin guard and 4a adds supplier API intakeNo catalogue API and no supplier portal exist for gift cards. Only CSV and manual uploadAPI intake is removed from the 3b margin guard and 4a. CSV and manual stay
33b and the 3b margin guard with 4a go into consecutive sprintsAkshay confirmed only the approval gate for this sprint. the 3b margin guard with 4a has an open question on the revenue engine3b is committed. the 3b margin guard with 4a waits on O5
4Phase 2 (2a, 2b, 4d) flows approved changes to clientsNobody knows if Merit may change a fixed-margin client price without client approval, for example for a large fixed-margin client. Supplier-switch behaviour is also undefinedPhase 2 (2a, 2b, 4d) is blocked until the accounts team answers on Tue 13 Oct, 17:00 GST
5Finance approvers named looselyNames in the transcript are garbled. Build Spec v1.1 is the sourceFaras Ismail or Amr AboKhalil
6The monthly email and propagation are one stepBuild Spec F13 sets 30-day notice. Tahsin said late updates cause loss. The two pull in opposite directionsNew open item O6

05Decisions for the tech team

At sprint planning on 13 Oct we ask for T1 to T3, one owner per build step, a size for 3b, and answers to T-Q1 to T-Q5. the 3b margin guard with 4a is sized after O5.

#DecisionProposalAfter the meeting
T1Where the supplier rate record and the approval queue liveIn the Merchandising Service, next to the current Online Catalogue data. Not in a new serviceOpen Needs T-Q1: where the supplier rate lives today
T2Intake orderCSV and manual upload in 3b. Supplier APIs later, and only if one existsSettled No API exists for gift cards
T3Ticket breakdownFour child tickets under MPS-1631, one per build step, each with its acceptance criteria. 3b first, written from the Build BriefOpen Tahsin creates the 3b ticket this week

06Open items O1 to O10

Each has an owner and a date. Four of them block Phase 2 (2a, 2b, 4d). Two decide the 3b margin guard and 4a.

3b
Starts 13 Oct
O3, O7 at sprint planning
3b margin guard and 4a
Waits
O5, O7
Phase 2 (2a, 2b, 4d)
Blocked
O1, O2, O4, O6
4c
Not written
Finance item 2
#Open itemOwnerDateBlocks
O1May Merit change a client's price automatically when a supplier changes? A large fixed-margin client may need to approve firstBrian and Tahsin, with the accounts teamTue 13 Oct, 17:00 GSTPhase 2 (2a, 2b, 4d)
O2What happens on a supplier switch, for a split client and for a fixed-margin client? What happens on a markup case when the margin changes?Brian and TahsinTue 13 Oct, 17:00 GSTPhase 2 (2a, 2b, 4d)
O3Alert channel for FinanceAkshay13 Oct sprint planning3b
O4Does the system accept revenue-share values per client today, or must we add them?AkshayBefore Phase 2 (2a, 2b, 4d) sizingPhase 2 (2a, 2b, 4d)
O5Is the revenue engine new, or a change to the existing computation?AkshayBefore 3b margin guard and 4a sizing3b margin guard and 4a
O6The 30-day notice (F13) against on-time updates. When does an approved change reach the client price?Brian, with Finance and the accounts teamTue 13 OctPhase 2 (2a, 2b, 4d)
O7Validation bounds for discount and fee. The Build Spec gives the FX guard and the VAT table, not discount boundsFinance, through BrianBefore 13 Oct sprint planningF6 in 3b
O8Rule check: at a 1.5 percent supplier discount, revenue share leaves Merit below the 2.5 percent floor. This is the margin inversion in Build Spec section 6Finance (spec open item 4)OpenPhase 2 (2a, 2b, 4d) values
O9Finance accepts that one person can propose and approveBrian, to confirm with Faras IsmailBefore go-livePolicy only
O10Add Rohit to the next calls. Tahsin confirms before each call if it is merchandise or gift cardsTahsin and BrianNext meetingMeeting quality

07Finance items from v0.1

These still stand. None of them blocks 3b or the 3b margin guard and 4a. They change values, not structure.

#ItemOwnerBlocks
2Source of the expiry term per brandFinance and catalogue team4c values
3Source of record for each client's contracted revenue shareFinance and Account ManagementPhase 2 (2a, 2b, 4d) values
4The pricing rules in section 6 are policy, not only current practice. Akshay also questioned the 2.5 percent floor at a 1.5 percent discountFinancePhase 2 (2a, 2b, 4d) numbers, not structure
7Breakage calculation fileMohamed FaridEvidence only

08Scope: data accuracy first, Odoo in 4c

The build makes the numbers correct and traceable. Odoo sits in 4c and is not a dependency for go-live. Go-live does not wait on the ERP, and the ERP does not wait on go-live.

Build · now

Data accuracy

Supplier rate gate, margin integrity, revenue calculation and month-end data. Rollout by entity: KSA, then UAE, then UK.

4c · later

Odoo ERP

Connect Odoo. Planned separately. Not a go-live blocker.

The revenue model comes from the Finance Sign-Off v1.7. Per the plan, Finance signed it off on 6 Oct. If the Doc and this page disagree, the Doc wins.