Weekly F-Team Alignment
Thursday 12 November 2026 · week of 5 to 12 Nov
The end-of-year scope is set: one storefront demo for any client. Merit ID works end to end on staging. Rewards Portal estimates follow the written specs.
This week
One scope, one list, and the gaps named.
EoY scope set
Merit ID 30 Nov
Rewards Portal
→ next · ← back · Esc all slides · F fullscreen · N notes · D dark
Open with the one line on the cover. Last week was "backend first". This week the backend-first plan became one end-of-year scope list, agreed row by row on 10 Nov.
Product · Brian Week of 5 to 12 Nov Marketplace, Platform, E-Commerce Solution, Merit App
The scope is decided; the dates now depend on a few inputs
0
Decisions on the year-end scope
Agreed row by row, 10 Nov
Year-end scope →
0 days
To Merit ID go-live
Merit staff in Saudi Arabia, 30 Nov
Merit ID →
0 days
To the Rewards Portal platform date
7 December target
Rewards Portal →
0
Linear rule breaks today
Up from 30 on 6 Nov
Linear →
Marketplace
Notify Me and pre-order: requirements done, build next Q4 is the store revamp only Gift cards paused
Platform
Fulfilment events to OMS in production OMS hotfix out, 11 Nov GCP: 9 P0 rows open
E-Commerce Solution
Year-end scope agreed Storefront admin rebuild started Rewards Portal specs pending
Merit App
Staging walkthrough passed Points plus card to QA SMS sender late
Shipped to the teams this week
Scope tree, 9 Nov comments in New World prototype Storefront admin screens Collections explainer Merit App enhancement list Ticket clean-up, 224 rows C-level slides Decision minutes
Green = done, amber = moving, red = late or blocked. Click a number tile to jump to its slide.
Product · Brian Agenda
Seven updates, last week's promises, then our dependencies
1
Year-end scope
One demo for any client
2
Merit ID
Live 30 November
3
Rewards Portal
One Linear project
4
Al Fursan
Store revamp, app concept
5
Support and fraud
Zoho Desk, fraud layer
6
Linear and Tintash
Hygiene, handover
7
Also this week
SAIB, HR, hiring, GCP
8
Last week's promises
Done, moving, late
Tiles are clickable if someone asks to jump.
1 · Year-end scope Decided 10 Nov E-Commerce Solution
By end of December, Merit can demo one storefront to any client
1
Ops set up the client
Storefront and admin, by script or by hand
2
Ops pick the products
In LiveOps; the client publishes or rejects
3
Member shops and pays
Phone login, Qi points or Moyasar card
4
Order is fulfilled
Events to OMS in production, flag off
In for December
Functions first, design second Per-client payment and points rules VAT by market Gift cards from MGC, no new logic
Not in December
Self-registration for clients Menu builder Apple Pay (registration starts now) Partial refund
Build status, 11 Nov
Services · nearly complete
Identity Catalogue Pricing Orders Fulfilment
Portals · 10 to 15 percent built
Storefront Admin Seller Portal LiveOps
3,000products
Seller Portal products for the demo store
2 to 3clients
Demo clients, picked by Julie
1engineer
Abdalrahman moves to the Rewards Portal
Sources: 2026 End-of-Year E-Commerce Deliverables MOM, 10 Nov; Albadarneh call, 11 Nov; Al Fursan scope tree
The scope tree is the one list; Linear follows it. Wshah's team confirms the fit. Legacy suppliers (Almanea, SACO, Jasani) join as new supplier integrations once the API list arrives. Consolidated seller orders move to LiveOps. Cancel by Merit is QA done.
2 · Merit ID Go-live 30 Nov Merit App, Merit staff in Saudi Arabia
Merit ID works end to end on staging; the SMS sender is late
Works on staging, 10 Nov
Phone login Qi connect and disconnect Gift card paid with Qi points Physical order with a test card Addresses
Linear projects, share done, 11 Nov
Checkout and payments 100%
Profile and address 94%
Order history 93%
Product search 90%
Product details 85%
Analytics 79%
Points plus card 64%
Wallet and balance 25%
Watch
SMS sender: staging still sends as "Cloud OTP" Points plus card goes through QA Real-number OTP test waits for the KSA team Lamya waits for the Merit ID API documents
Sources: Merit App staging walkthrough MOM, 10 Nov; Merit ID internal launch plan, 3 Nov; Linear World 1 projects, 11 Nov
Hover each dot for the step and owner. Red ring = late, filled = done. The release stays small: staff use the app in production and leadership sees progress. Arabic is Q1 2027. Sender registration takes 7 to 10 working days. Qi is already connected (sync and balance); Fuad tests the purchase path today.
3 · Rewards Portal Top priority Platform date 7 Dec
Rewards Portal requirements sit in one Linear project; estimates follow the written specs
80 to 100clients
Migrate by end of December
1engineer
Abdalrahman, full time on the super key work
W1-1583 MGC reads the client ID Akshay
W2-923 Cognito users to Firebase Tamer · 3 to 4 Dec
W1-1590 Per-client pricing Yousef
W1-1585 Old order history Habeeb · P3
W1-1602 Payout API Wshah
How the estimate comes
1 Specs written: Fayez and Habeeb
2 Albadarneh hands them to engineering
3 Wshah sizes each item, then dates
Sources: Rewards Portal dependencies call, 10 Nov; Rewards Portal Go-Live Requirements project, 12 Nov
Keep the tone factual: the work is planned and tracked; the estimate waits for written specs. The 20 Nov target for the e-commerce parts moves with the specs. Also needed: multi-currency (pricing, orders, catalogue) and payout staging credentials and test wallets. MGC client ID waits on MPS-1688.
4 · Al Fursan Old world and app Marketplace, Al Fursan app
Al Fursan Q4 is the store revamp only; gift cards are paused
Al Fursan Store
Notify Me and pre-order: requirements done, not built yet Saudia OTP test passed Q4: store revamp only, to confirm with Thamer Pre-order runs next to the change request Three OTP fixes left (Rahul) Gift cards paused, 11 Nov
Customer care ticket flow, 5 Nov
1 Member asks for help
2 Fraud check first
3 Self-fix steps
4 Ticket, agent adds root cause
Arrival dates on checkout need Saudia approval.
Al Fursan app
9 Nov Standalone app presentation
Deck v7 Posted by Albadarneh
11 Nov ForLife app concept session
Next MMP and a launch month
Albadarneh now runs the e-commerce project and its stand-up.
~200per 1,000 orders
Customer care cases, 1 to 14 Oct. Target is 50
1 in 3tickets
A member asks before the promised time
24 hwait
Gift card wait without OTB, so OTB goes on first
Sources: Customer care tickets MOM, 5 Nov; ForLife walkthrough MOM, 9 Nov; Albadarneh call, 11 Nov
Ticket categories go to Raneem for validation (Mawi). Miles failures still have no answer for members. Work before the client signs the change request can be wasted; the team accepts that risk for pre-order.
5 · Support and fraud Decided 9 and 11 Nov Operations, Data, Product
Support gets one platform; the fraud layer starts in December
Zoho Desk rollout · owner Mawi · subject to budget
Now Contact Us goes to a Google Group
End of 2026 B2C Super App and B2B Super Platform
February 2027 Al Fursan
March 2027 CIB
Fraud layer, decided 9 Nov
December Transaction level on OMS data
Later User level through one customer data platform
Merit's own layer Any tenant, not only Al Fursan No hold on Al Fursan orders
Still to agree
1 Field list Ruba
2 OMS fields Marthino
3 What we capture, from when Brian
SAR 250kin one day
Al Fursan gift card fraud loss, reported 4 Nov
DecemberMVP
Transaction-level fraud check on OMS data
4front ends
Move to Zoho Desk by March 2027, if the budget is approved
Sources: Support Center and Zoho Desk MOM, 11 Nov; Fraud Gate Data MOM, 9 Nov
Each front end builds its own support entry point from Customer Care's spec. Al Fursan handles its own fraud.
6 · Linear and Tintash Daily rule check World 1, 2 and 3
Linear hygiene slipped this week; Tintash stays to 30 November
Linear rule breaks per daily check
Today's 108 breaks
102 no squad label
Squad label 102 Product label 5 Initiative 1
53 assigned 55 no assignee
Tintash handover
Handover sessions done, except Wallet LiveOps Wshah reassigns 294 World 1 issues Tintash and the Jira sync end 30 Nov
Sources: Linear daily rule checks, 6 to 12 Nov; Khawar, 6 Nov
Correction from last week's deck: Tintash does not leave this week; they stay until the end of November. Most new breaks are Super App QA bugs. Of the assigned ones: Elias 18, Israa 10. Linear held 2,647 issues on 9 Nov.
7 · Also this week Four updates
SAIB needs an onboarding owner; HR onboarding waits for two inputs
SAIB Aseel, 5 Nov
Owner needed
for merchant onboarding
No go-live without merchant self-registration Timeline goes to SAIB after signature Raouf drafts the internal scope
HR onboarding, 10 Nov
~20 Nov
version 1
1 Offer from the template
2 DocuSign, by hand
3 ZenHR record, HR reviews
Waits for templates and ZenHR access
Hiring
Mon 16 Nov
PM panel interview
Offer for Riham is ready Mid PM: interviews first Junior PM profiles in from Rita
GCP incident
9
P0 rows open on day 9
Travel Shop keys rotated PII encryption plan, Brian Each PM tracks key swaps
SAIB merchant paths
Online: keep current codes Small offline: Merit web POS Large chains: own POS Prototype: 15 screens, English and Arabic
HR onboarding, decided
DocuSign stays manual System creates the ZenHR record Joiner notice: name and title only Template by entity
Sources: SAIB Aseel way of working MOM, 5 Nov; HR onboarding review MOM, 10 Nov; daily briefings 10 and 11 Nov
SAIB: small offline merchants use the Merit web POS, large ones integrate their own POS. Brian presents the self-registration concept. Prototype: 15 screens, 4 flows, English and Arabic. HR: joiner notice carries name and title only.
8 · Last week's promises From the 5 Nov deck
Of last week's commitments, one is done and three are late
1 done 5 moving 3 late
Promised on 5 Nov Status Where it stands
One support plan , Zoho statusDone Mawi's plan in #f-team; dates set 11 Nov, budget pending
Year-end scope (was: size wave B)Moving Agreed row by row 10 Nov; Wshah's fit check still open
Merit ID build , login and import by 13 NovMoving Staging passed 10 Nov; account import due 13 Nov
Points feed from TamerMoving Qi connected; purchase test due today (Fuad)
Al Fursan app MMP and Justin sessionMoving Presentation 9 Nov, deck v7, ForLife 11 Nov
Tintash issues to Merit ownersMoving 294 left on 6 Nov; deadline now 30 Nov
SMS sender by 10 NovLate Staging still sends as "Cloud OTP"
Fraud data field list by 6 NovLate Direction set 9 Nov; field list not agreed
MGC tenant ID date , Identity BRDsLate No date or document logged this week
Read only the three late rows aloud. The MGC client ID item now sits in the Rewards Portal Go-Live Requirements project (W1-1583), waiting on MPS-1688.
Dependencies What our team needs
Four inputs our team depends on to keep the dates
1
Written specs for the Rewards Portal items
Our estimates start as each spec comes in.
From Habeeb and Fayez, through Albadarneh
2
The Merit SMS sender ID
Go-live on 30 Nov needs the Merit sender.
From Marthino's team
3
The legacy supplier API list
It lets Almanea, SACO and Jasani join the new Seller Portal.
From Marketplace team (Aditya)
4
An owner for SAIB merchant onboarding
Self-registration is a go-live condition.
From Fred
Also watching
MGC client ID, waits on MPS-1688 Fraud data field list 108 Linear rule breaks 9 GCP P0 rows open
MGC client ID: W1-1583, Akshay builds it from Rohit's plan. Fraud data: field list from Ruba, OMS fields from Marthino.
Next week 13 to 30 Nov
Next week: roadmap 2027, Linear on the scope, the Merit ID pilot path
Roadmap Merit ID E-commerce Rewards Portal People
This week
Linear matches the scope tree
Fulfilment test on staging with Fuad
Specs in, then Wshah sizes
Fri 13 Nov
Roadmap 2027 to Fred
Account import
HR templates from Dayana
Mon 16 Nov
Wallet screen
PM panel interview
Fri 20 Nov
LiveOps view
HR onboarding version 1
Mon 30 Nov
Live for KSA staff
Tintash leaves, Jira sync ends
Owners
Roadmap Roadmap 2027 Brian
E-com Linear on the scope tree Brian
E-com Fulfilment test Fuad
Merit ID Account import Brian
Merit ID Wallet screen Elias
Merit ID LiveOps view Marthino's team
RP Written specs Fayez, Habeeb
People HR templates Dayana
People HR version 1 Brian
The first column has no fixed day: the scope tree work, the fulfilment test and the Rewards Portal specs all run this week.
MERIT Product Brian Arfi Faridhi
Thank you
One year-end scope. Merit ID on 30 November. Rewards Portal specs next.
“Measure a thousand times, cut once.”
Turkish proverb
Questions
Dependencies: Rewards Portal specs, SMS sender, supplier APIs, a SAIB owner.