BiWeekly Core Product · Thu 29 Oct 2026 · Brian
E-Commerce, Al Fursan and B2C:
what moved since 13 October
Covers 14 to 29 Oct. Source: weekly reports of 15 and 22 Oct, plus 23 to 29 Oct from Slack, ledgers and standups.
Al Fursan migration
February deadline is at risk. We re-scope to a must-have core and tell Fred on 2 or 3 Nov.
Tintash exit, this week
Handover is mostly done. Four gaps stay open.
Linear
Live next to Jira. AFM board moved 26 Oct. Jira sync ends 30 Nov.
→ Space next · ← back · Esc grid · F fullscreen · N notes · T theme
Notes
Open with the three tiles. Ask for decisions at slide 8. Everything else is read-ahead.
Delivered since 13 Oct
New-platform services are in production and every common service has an owner
Platform and delivery
- Plan B locked in writing 16 Oct: canary 8 Jan 2027, full switch end of January
- All 19 common services have owners (21 Oct session)
- In production 20 to 21 Oct: storefront v1.0.0, storefront portal backend v1.0.0, seller portal backend v1.2.0, PIL v1.4.0. Pricing service v1.1.0 also live
- Homepage UI/UX live 21 Oct (MP-12320)
Commercial and process
- Linear live: two-way sync passed 21 Oct, AFM board imported 26 Oct
- STC Apple: evidence pack sent 16 Oct, agreement signed 21 Oct
- Legal: Pre-Order terms reviewed. Partial refund as store credit answered 28 Oct (MLSP-1467)
- Omniful one-pager and proposal video sent 26 Oct
- Al Fursan Standalone: Fred named me PM lead 22 Oct
Notes
Read fast. STC production credentials still not released at last check. Giftomatic is live on 3 UAE clients (Platform).
Al Fursan migration · risk
The February deadline is at risk; we cut to a must-have core before we tell Fred
Where we are
- ~280 days of estimated E-Commerce work (Wshah, 21 Oct)
- Aligned 28 Oct (Albadarneh, Wshah, Mawi, me): we tell Fred now that February is at risk
- Al Fursan QA, 25 Oct: 10 of 75 cases failed
- Fred's direction 13 Oct: smaller releases, critical part first. We can do it, but risk stays and the re-scope needs more time
Re-scope plan
- Fri 30 Oct: I cut the backlog to a must-have core and mark low-visibility features to delay
- By Mon 2 Nov: Wshah tags the same tickets P0 to P3 with estimates. P0 and P1 are must-have
- Added to scope: the new Seller API, because API sellers do not move to the Seller Portal
Next: team call Mon 2 Nov, then the update to Fred on Mon 2 or Tue 3 Nov.
Notes
Source: 28 Oct migration call. Risk named there: if Saudia sees paused features, the team races to finish them. Focus block booked Fri 30 Oct 19:30 to 21:30.
Tintash exit · end of this week
Most of the Tintash handover is done; four gaps must close by Friday
Done or landing
- 12 handover sessions done. Identity is today
- Albadarneh runs the daily standup
- Multi-currency 90 to 95% (Zarar)
- Catalog Sync, Price API, Bulk Upload: production expected in 1 to 2 days (28 Oct)
- Zarar stays to end of November
Open
- Fulfillment Service stuck in staging, some tickets failed QA
- B2C secrets for 3 environments not received from Tintash
- 552 Linear issues still on Tintash names, to reassign
- Wallet, Payment, Merit Utilities, Translation wait for a new director or engineer
Notes
If secrets do not arrive before Friday, Merit loses access. Ask Habeeb or Wshah who chases Khaled today.
Saudia · Drops 3 and 4
Three BRDs are due today; the Drop 4 cut is still not signed
Scope
- Due today: BRDs for Bundle, AppleCare, Comparison. Comparison waits on spec rows from Akshay
- Drop 4 cut: 4 items in 2026 (both OTPs, Coming Soon with Pre-Order and Sold Out, Apple Store batch 1). The rest moves to Q1 2027 on the new platform
- Pre-Order phase 1: 1 unit per order line
Live issues
- Care cases: 199 per 1,000 orders (1 to 14 Oct). Target is 50
- Checkout OTP BRD v2.0 is with Rahul
- Gift Card OTP not live: waits on sender ID and the BAB SMS gateway
Notes
Gift card codes and "where is my order" are 67% of October cases. Drop 4 build order decisions (DEC-0455 to 0459) are mine and still open.
Payments and refunds · with Tamer and Thino
Partial refunds can move to Phase 2; external partners only reverse the full burn
- Legal accepts partial refund as store credit (MLSP-1467, 28 Oct). Phase 2 design opens
- External loyalty partners cannot refund part of a burn. They reverse the whole transaction (Tamer)
- Moyasar does not support N charges with one 3DS step. Hamd asks Moyasar support
- Mixed payment (card plus points) backend from Elias is ready for review
- Burn Adapter: one Linear project. Hashem's "Burn Adapter for Al-Fursan" stays and I archive mine (agreed 28 Oct)
Notes
Ask Tamer whether the reversal limit applies to Comarch Miles too (Akshay had a Comarch answer 20 Oct).
B2C Super App and Rewards
B2C sign-in waits on the OTP service, due end of October
- OTP and notification service: due end of October (Thino). Unblocks B2C sign-in and migration OTP
- WhatsApp OTP (Unifonic): end of December target
- Exchange Hub is on staging. Next: multi-currency sales channel, country and currency filters, discount sort at the E-Commerce Core source
- Tenant fees and discounts (MSP-566): waiting on the QA date from Yousef
- Location-based visibility: QA closed 21 Oct; MBA-429 release waits on branch conflicts
Notes
Thino: confirm the OTP date is still end of October. I still owe staging access (COM-1439).
Decisions for this room
Two calls to close today, and one proposal
| # | Decision | Who decides | Open since |
| 1 | Payment integration service owner: Thino's team or Tamer | Fred, Thino, Tamer | 13 Oct |
| 2 | Settlement Service (AFM-14.1): which team builds the final money calculation per order | Fred, Habeeb | 16 Oct |
| 3 | Proposal, roadmap format (from 13 Oct): each lead writes the roadmap in a Google Doc, then we turn it into a slide artifact like this one | Fred to agree | 13 Oct |
Notes
1 and 2 were also open at the last meeting. If 1 stays open, the Al Fursan payment work has no owner after Tintash leaves.
Next two weeks
Five dates to watch
| Date | What |
| Thu 29 Oct | Al Fursan Standalone kickoff 16:00. Al Fursan Pay position: build, Hyperpay, or white-label |
| Fri 30 Oct | Must-have re-scope of the Al Fursan migration backlog |
| 31 Oct | Most of Tintash leaves. Secrets, Fulfillment Service and issue reassignment must close |
| Mon 2 / Tue 3 Nov | Update to Fred: February at risk, must-have scope, P0 to P3 estimates. Then the Drop 4 cut with Saudia and partial refund Phase 2 |
| 16 Nov / 30 Nov | Runa 5 req/s limit goes live. Jira sync ends, Zarar leaves |
Notes
My own open items to mention only if asked: E-Com 3-month roadmap (COM-1201), enterprise pricing grid (COM-1254).