Merit · Al Fursan Apple Store · Proposal
The delivery plus 14 day rule answers every order whose outcome we know. This is about the ones we do not: still in transit, delivery never recorded, a return still open. Right now they have no ending at all.
One sentence: without a delivery event the release condition never fires, so the cashback waits forever and nobody is watching it.
14
days after delivery. The release trigger now in effect, replacing payment plus 30, per DEC-0180.
14
days from delivery. Also the return window, so release now lands right on that boundary.
0
ways to reverse a credit. The Accenture Sales Accrual API is credit-only.
Release condition, as written today
There is one condition now, not two. Without a delivery event it never fires, and there is no second branch left to fall back on.
Credit only a delivered, uncontested order. Watch the pending pile daily. Put someone in front of it.
Every path ends in a full credit or no credit. Nothing partial, nothing reversed, because nothing can be reversed.
Three orders, same rule. Only the third one is new behaviour.
Day 0 onward, three order tracks
The first two tracks show the rule now in effect: delivery plus 14 days, nothing else. The third track never gets a delivery event, so it stays pending, watched by the daily exception list, until the standard non-delivery refund closes the order.
Nothing in the message. It stays "Earn XX miles as cashback on this purchase", with no timing claim attached, so no product copy or commercial term moves.
The member also waits less. A normal Apple Store order delivers in 3 to 5 days, so the wait now runs about 17 to 19 days instead of 30.
If Saudia publishes a number in an FAQ or in the terms, it should read 14 days after delivery, provided the order is not returned. A flat number from purchase date no longer holds, because timing depends on when the item arrives.
Two fewer things to confirm now. One thing left.
A delayed shipment needs no special rule now. Release keys off delivery, so a late shipment simply pushes its own 14-day clock forward. The day-45 ceiling needs no confirmation either, because it no longer exists.
| Ask | How to frame it | If Saudia says no |
|---|---|---|
| 1. The terms wording, if a timing figure is published anywhere | One clause, added once, stating 14 days after delivery | A member with a delayed order can point at a published promise we did not meet |
The commercial position is unchanged. This covers only the release mechanics, corrected to match delivery per DEC-0180, and does not reopen the earn rate or anything agreed on 20 July.
Both of these exist whether or not this proposal is adopted.
01 · daily
The daily exception list. Two conditions, not one. First, an order with no delivery event 31 days after payment. Second, an item delivered more than 14 days ago with no miles credited. Each row carries the last known status and the age. Operations can pull this list by hand during soft launch. This is now the only mechanism that surfaces a stuck order.
A flat day-31 cutoff would raise a false alarm on every slow shipment that is still moving, because the release clock now starts at delivery rather than at payment.
02 · every order
The delivery event itself. Under manual fulfilment a person marks the order delivered, and cashback release keys off that mark.
The choice does not go away. It just gets made by an implementation detail instead of by us.
Outcome A
A wrongly marked delivery credits an order that never actually arrived. Permanently, and without recourse, because the API cannot claw back.
Outcome B
The cashback silently never arrives. No delivery event ever gets recorded, release never fires, and nobody on our side has a queue to look in.
Both land inside the first month of a launch timed to the iPhone 18.
| Apple Store Cashback Scenario Flow (Phase 1) | Google Doc |
| BRD v2.3, AlFursan Store Earn Model. Authoritative on commercial terms | Google Doc |
| PRD v1.5, Store Earn Model (Cashback) | Google Doc |
| Habeeb's Apple Store testing and launch plan, 16 August | Slack |
| Apple Store go-live dependency tracker | Sheet |
| AlFursan Master Project Plan | Sheet |
| The two-pager this explainer accompanies | Google Doc |
Prepared by Merit Product, 19 August 2026. Tracked internally as DEC-0173.