Saudia's table has 16 rows. The four Low and Lowest rows are out. The other 11 rows get dated steps, an owner per step, and one publish date.
Most items publish on 9 or 10 Dec, just before the code freeze. Four items have a gate: if a third party does not commit by its date, the item moves to 2027.
| Workstream | Requirement | Priority | Plan |
|---|---|---|---|
| OTP & Security | Gift Card OTP Flow | Highest | in scope |
| Phase 2: OTP at Checkout | High | in scope | |
| Apple Store | Discoverability, Mobile View | High | in scope |
| Cashback | Lowest | out of scope | |
| Product Comparison | Mid | in scope | |
| AppleCare | Mid | in scope | |
| Bundle Products | Mid | in scope | |
| Buy Now Pay Later: Tabby | Mid | in scope | |
| Promo Codes | Promo Code Enhancements | Low | out of scope |
| Product Availability | Coming Soon Products | High | in scope |
| Pre-order | High | in scope | |
| Sold Out Journey | High | Completed | |
| Future Drops 2026 | Notification Hub | Lowest | out of scope |
| Overall UI/UX revamp | Highest | in scope | |
| Rush Delivery | High | in scope | |
| eSIM | Lowest | out of scope |
Switched on for members. Ops and CS briefed. Saudia announces where needed.
A date where a third party must commit. If they do not, the item moves to 2027 and Abdulelah hears it in writing.
Code freeze is Thu 10 Dec. Every release lands before it.
Today: Built. Waits on the Saudia sender ID on Unifonic.
| Thu 15 Oct | Confirm the sender ID letter is signed and with Unifonic (activation takes 7 to 10 business days) | Rahul | |
| Tue 20 Oct | Merge the Ops and CS feedback changes | Arpan | |
| Wed 21 Oct | Sender ID active on Unifonic | Saudia, Rahul | |
| Thu 22 Oct | UAT with Saudia on the live SMS route | Rahul, Saudia | |
| Sun 25 Oct | Saudia go-live approval, in writing | Albadarneh | |
| Mon 26 Oct | Release to production | Arpan | |
| Tue 27 Oct | Publish: gift cards back on sale with OTP. CS briefed. Saudia announcement | Rahul, Saudia marketing | |
| Tue 3 Nov | One-week check: OTP success rate, fraud cases, CS tickets | Brian |
Risk: Sender ID. Each day it is late moves every date by one day. Latest publish: Thu 12 Nov.
Today: BRD with Saudia. Rahul sent 9 questions. Paused on the 13 Oct roadmap, first priority for Abdulelah on 14 Oct.
| Sun 18 Oct | Answers to the 9 questions (Abdulelah promised them 15 or 16 Oct) | Abdulelah, Amr | |
| Wed 21 Oct | Workshop with Shahad (Saudia fraud team): account takeover and fraudulent redemption | Brian, Rahul | |
| Tue 27 Oct | Final BRD: SMS only, non-Saudi numbers blocked, address lock, fewest clicks | Brian | |
| Thu 29 Oct | Saudia sign-off and CR | Albadarneh | |
| Thu 5 Nov | OTP step design in checkout, EN and AR | Raneen | |
| Thu 5 Nov | Estimate and tickets | Aditya | |
| 8 to 26 Nov | Build | Marketplace engineering | |
| 29 Nov to 1 Dec | Internal QA | QA | |
| 2 to 3 Dec | UAT with Saudia, with fraud team scenarios | Rahul, Saudia | |
| Sun 6 Dec | Saudia go-live approval | Albadarneh | |
| Tue 8 Dec | Release to production | Marketplace engineering | |
| Wed 9 Dec | Publish: OTP on at checkout. CS script. Member notice | Rahul, Saudia |
Risk: Uses the same SMS route as the Gift Card OTP. Needs you to unpause it.
Today: Raneen showed home, PLP and mobile on 14 Oct. Saudia wants a new product page and a mobile-first approach.
| Thu 15 Oct | Short brief on the new design for Content Square: the functions agreed on 14 Oct. Abdulelah asked for it to prepare the workshop | Brian, Raneen | |
| Sun 18 Oct | New product page: specs and description in expandable bars, short mobile page | Raneen | |
| Tue 20 Oct | Content Square workshop. Abdulelah sends the invite. Show mobile first, no images in advance | Abdulelah, Brian, Raneen | |
| Thu 22 Oct | Confirm the member Miles balance is available to the storefront ("Shop within your balance", "Chosen for you") | Aditya | |
| Thu 29 Oct | Design freeze 1: home, PLP, mobile menu. Saudia approves | Raneen, Abdulelah | |
| Thu 5 Nov | Design freeze 2: product page, category page, balance sections, "Chosen for you" logic | Raneen, Brian | |
| 1 to 26 Nov | Front-end build, web and mobile. Home and PLP from 1 Nov, the rest from 8 Nov | Marketplace engineering | |
| Thu 26 Nov | Relaunch banners in two sizes, EN and AR | Naif (Saudia marketing) | |
| 29 Nov to 1 Dec | Internal QA on mobile devices, EN and AR | QA | |
| 2 to 6 Dec | UAT with Saudia | Rahul, Saudia | |
| Mon 7 Dec | Saudia go-live approval | Albadarneh | |
| Wed 9 Dec | Release to production behind a switch, before the 10 Dec freeze | Engineering | |
| Fri 18 Dec | Publish: switch on for the anniversary relaunch. It can go on 10 Dec if Abdulelah agrees | Saudia, Rahul | |
| 18 to 24 Dec | Content Square check on the new pages | Brian |
Risk: Largest item. One designer carries it.
Today: Bucket 1 (front end only) in progress. Bucket 2 needs a design from Raneen. Legal question on Apple images open.
| Thu 15 Oct | Confirm what bucket 1 has shipped and what is left | Rahul | |
| Thu 22 Oct | Legal answer: can we use Apple marketing images | Albadarneh, Saudia legal | |
| Thu 22 Oct | Bucket 2 mobile design, matched to the revamp menu (brand store in the menu) | Raneen | |
| Tue 27 Oct | Saudia approves the design | Rahul | |
| Thu 29 Oct | Release and publish bucket 1 | Engineering | |
| 1 to 12 Nov | Build bucket 2 | Engineering | |
| 15 to 17 Nov | QA and UAT with Saudia | QA, Rahul | |
| Wed 18 Nov | Saudia go-live approval | Albadarneh | |
| Thu 19 Nov | Release and publish: Apple Store easy to find from the mobile home and menu | Engineering, Rahul |
Risk: Raneen also carries the revamp. Keep this design small and reuse the revamp menu.
Today: Sold Out is live on the Apple Store only. This plan extends it to the whole store. BRD v0.8 (15 Oct) is the latest.
| Thu 15 Oct | Decide product level or variant level | Aditya, Akshay | |
| Thu 15 Oct | BRD v0.8 is the latest (v0.7 already sent). Saudia reviews it | Brian | |
| Wed 21 Oct | Estimate for each mode | Aditya, Akshay | |
| Thu 22 Oct | Pre-order unit cap and label wording | Raneem Ajana | |
| Thu 29 Oct | Saudia sign-off and CR | Albadarneh | |
| Thu 29 Oct | Design: Notify me button, Coming Soon label, Pre-order badge and checkout (inside the revamp product page) | Raneen | |
| Thu 5 Nov | Saudia approves message templates, EN and AR (Notify me email and SMS, cart message) | Heba, Saudia | |
| Thu 12 Nov | First pre-order event product, supplier ship date under 30 days | Rahul, partnerships | |
| 25 Oct to 19 Nov | Build in order: Sold Out store-wide, then Coming Soon (from 1 Nov), then Pre-order (from 8 Nov) | Marketplace engineering | |
| 22 to 26 Nov | QA and UAT with Saudia | QA, Rahul | |
| Sun 29 Nov | Saudia go-live approval | Albadarneh | |
| Tue 1 Dec | Release to production, every mode off by default | Engineering | |
| Thu 3 Dec | Publish Coming Soon: Ops switches on the first products. CS briefed | Ops, Rahul | |
| Thu 10 Dec | Publish Pre-order with the first event product. Auto refund if not delivered in 28 days | Ops, Rahul |
Risk: Estimates missing since 8 Oct. Moyasar cannot refund cards after 30 days.
Today: No courier or service chosen. Mostly a logistics problem. Rahul did not promise it on 14 Oct.
| Thu 22 Oct | BRD: cities, cut-off time, fee, delivery promise | Brian | |
| Thu 22 Oct | Ops names an owner and lists courier options in Riyadh and Jeddah | Mawi, Wael (Ops) | |
| Thu 5 Nov | Discovery done: courier, cost per order, which sellers can hand over the same day | Ops | |
| Thu 12 Nov | GATE: go or no-go with Saudia, fee approved. No-go goes to Abdulelah in writing, moves to 2027 | Brian, Albadarneh | |
| 15 Nov to 2 Dec | Build: delivery option at checkout, fee, order routing | Engineering | |
| 3 to 6 Dec | QA, UAT and a dry run with the courier | QA, Ops | |
| Mon 7 Dec | Saudia go-live approval | Albadarneh | |
| Tue 8 Dec | Release to production | Engineering | |
| Thu 10 Dec | Publish in one city first | Ops, Rahul |
Risk: The service may not exist in the market at a fee Saudia accepts.
Today: New. No BRD.
| Thu 22 Oct | Check Apple product specs are structured fields in the catalog | Akshay | |
| Thu 29 Oct | BRD: compare up to 3 Apple products of the same type | Brian | |
| Thu 5 Nov | Saudia sign-off | Rahul | |
| Thu 12 Nov | Design, EN and AR | Raneen | |
| 15 Nov to 2 Dec | Build | Engineering | |
| 3 to 6 Dec | QA and UAT | QA, Rahul | |
| Mon 7 Dec | Saudia go-live approval | Albadarneh | |
| Tue 8 Dec | Release to production | Engineering | |
| Thu 10 Dec | Publish on the Apple Store | Rahul |
Risk: If specs are free text, Ops must fill fields for every Apple product first.
Today: New. Discussed in the July workshops, no BRD.
| Thu 22 Oct | Saudia lists the first bundles (for example iPhone, case, charger) and the price rule | Rahul, Saudia | |
| Thu 29 Oct | BRD: a bundle is one catalog product, stock equals its lowest part, one price in Miles | Brian | |
| Thu 5 Nov | Saudia sign-off | Rahul | |
| Thu 12 Nov | Design: bundle card and product page | Raneen | |
| 15 Nov to 2 Dec | Build | Engineering | |
| Thu 3 Dec | Ops sets up the first bundles | Ops | |
| 3 to 6 Dec | QA and UAT | QA, Rahul | |
| Mon 7 Dec | Saudia go-live approval | Albadarneh | |
| Tue 8 Dec | Release to production | Engineering | |
| Thu 10 Dec | Publish the first bundles on the Apple Store | Ops, Rahul |
Risk: A real bundle engine does not fit before December. One catalog product per bundle does.
Today: Dropped for the July launch. The product page sections are hidden in Figma and can come back.
| Thu 22 Oct | GATE: a supplier can sell AppleCare (codes, price per device, activation). No supplier means 2027 | Rahul, partnerships | |
| Thu 29 Oct | BRD: add-on on the product page and in the cart, how the member receives it | Brian | |
| Thu 5 Nov | Saudia sign-off. Design: un-hide the existing Figma sections | Rahul, Raneen | |
| 8 to 26 Nov | Build | Engineering | |
| 29 Nov to 3 Dec | QA and UAT | QA, Rahul | |
| Sun 6 Dec | Saudia go-live approval | Albadarneh | |
| Tue 8 Dec | Release to production | Engineering | |
| Thu 10 Dec | Publish on Apple product pages | Rahul |
Risk: Depends on a supplier contract, not on engineering.
Today: No owner, no contract. Three parties: AlFursan, Tabby, Merit. Rahul did not promise it on 14 Oct.
| Sun 18 Oct | Tamer names a commercial owner | Tamer | |
| Thu 29 Oct | Intro call with Tabby, draft of the three-way terms | Tamer | |
| Thu 5 Nov | BRD: where Tabby shows, Miles plus card split, refunds | Brian | |
| Thu 12 Nov | GATE: terms signed and Tabby merchant account open. Not signed means 2027, in writing to Abdulelah | Tamer, Albadarneh | |
| 15 Nov to 3 Dec | Integration and Tabby test sign-off | Engineering | |
| 6 to 7 Dec | UAT and Saudia go-live approval | Rahul, Albadarneh | |
| Tue 8 Dec | Release to production | Engineering | |
| Thu 10 Dec | Publish at checkout on the Apple Store | Rahul |
Risk: Past cases spent two months on terms before tech could start.
Revamp, Checkout OTP, Drop 4, Apple mobile, Rush, Comparison, Bundles, AppleCare and Tabby all build between 25 Oct and 3 Dec, on the Marketplace team outside Jordan. Aditya names an owner per build by Thu 22 Oct.
Raneen designs the revamp, Apple mobile, Drop 4 screens, Comparison, Bundles and AppleCare. Revamp first, the rest reuse its parts.
Sign-offs, CRs, templates and go-live approvals land from 29 Oct to 7 Dec. Each late approval moves its publish date by the same days.
Cut order if capacity is short: AppleCare, then Tabby, then Product Comparison, then Bundle Products. All four are Mid.
Yes. Abdulelah ranks it first. Publish 9 Dec. Promo Codes stay paused (Low).
Yes, in writing. AppleCare 22 Oct, Rush and Tabby 12 Nov. A missed gate means 2027.
Ask Aditya to name one owner per build on the Marketplace team by Thu 22 Oct.
Ready 9 Dec behind a switch. Offer Abdulelah 10 Dec. If he wants the anniversary, it goes on 18 Dec.
| Date | Action | Owner |
|---|---|---|
| Thu 15 Oct | Short brief on the new design for Content Square: the functions agreed on 14 Oct (Abdulelah asked for it) | Brian, Raneen |
| Thu 15 Oct | Gift Card OTP: is the sender ID letter signed and with Unifonic? Which date does Unifonic activate it? | Rahul |
| Thu 15 Oct | Apple Store mobile: which bucket 1 front-end changes are live, and which are left? | Rahul |
| Thu 15 Oct | BRD v0.8 (Coming Soon, Pre-order) is the latest. Saudia sign-off due Thu 29 Oct | Brian, Albadarneh |
| Sun 18 Oct | Tabby owner named. Answers to the 9 OTP questions | Tamer, Abdulelah |
| Tue 20 Oct | Content Square workshop | Abdulelah, Brian, Raneen |
| Wed 21 Oct | Shahad workshop on Checkout OTP | Brian, Rahul |
| Thu 22 Oct | Build owners from Aditya. Rush BRD. AppleCare supplier gate | Aditya, Brian, Rahul |
No engineering estimate exists for any item except the built Gift Card OTP. Build windows are my proposal.
Comparison, Bundles and AppleCare have no BRD and no prior scope beyond July notes. Their plans start from zero.
Every publish date assumes Saudia approves on the planned day.
Garbled around minutes 40 to 60 of the 14 Oct workshop. Re-listen before quoting.