Al Fursan · Saudia's priority table · draft for Brian · 15 Oct 2026

Ten plans, each running from requirement to publish by 10 December

Saudia's table has 16 rows. The four Low and Lowest rows are out. The other 11 rows get dated steps, an owner per step, and one publish date.

The idea in one sentence

Most items publish on 9 or 10 Dec, just before the code freeze. Four items have a gate: if a third party does not commit by its date, the item moves to 2027.

→ / Spacenext slide←previous slideEscall slides FfullscreenNspeaker notesTlight or dark
Sources: Saudia priority table (Rahul's screen, 14 Oct), workshop recording 14 Oct, MOMs 2, 6, 13 Oct, Q4 Drop Plan v0.2
Saudia's table

Eleven rows stay in, four Low and Lowest rows are out

WorkstreamRequirementPriorityPlan
OTP & SecurityGift Card OTP FlowHighestin scope
Phase 2: OTP at CheckoutHighin scope
Apple StoreDiscoverability, Mobile ViewHighin scope
CashbackLowestout of scope
Product ComparisonMidin scope
AppleCareMidin scope
Bundle ProductsMidin scope
Buy Now Pay Later: TabbyMidin scope
Promo CodesPromo Code EnhancementsLowout of scope
Product AvailabilityComing Soon ProductsHighin scope
Pre-orderHighin scope
Sold Out JourneyHighCompleted
Future Drops 2026Notification HubLowestout of scope
Overall UI/UX revampHighestin scope
Rush DeliveryHighin scope
eSIMLowestout of scope
Source: table on Rahul's screen in the 14 Oct workshop. Out of scope: Cashback, Promo Codes, Notification Hub, eSIM.
What "plan" means here

Every item runs the same ten steps, and it is done only when it is published

RequirementBRD or answersSign-offSaudia and CRDesignRaneen, EN and AREstimateticketsBuildQAUATwith SaudiaApprovalSaudia go-liveReleaseproductionPublishon for membersevery plan, in this order

Publish

Switched on for members. Ops and CS briefed. Saudia announces where needed.

Gate

A date where a third party must commit. If they do not, the item moves to 2027 and Abdulelah hears it in writing.

Freeze

Code freeze is Thu 10 Dec. Every release lands before it.

Some items skip a step: Gift Card OTP is already built.
The plan on one page

Builds pile up in November; most items publish 8 to 10 Dec

Prepare, sign-off, designBuildQA, UAT, approvalGatePublish
Dates are proposals. Only Gift Card OTP is built today. No estimates exist for the rest.
1 of 10 · OTP & SecurityHighest

Gift Card OTP Flow: publish Tue 27 Oct

Today: Built. Waits on the Saudia sender ID on Unifonic.

Thu 15 OctConfirm the sender ID letter is signed and with Unifonic (activation takes 7 to 10 business days)Rahul
Tue 20 OctMerge the Ops and CS feedback changesArpan
Wed 21 OctSender ID active on UnifonicSaudia, Rahul
Thu 22 OctUAT with Saudia on the live SMS routeRahul, Saudia
Sun 25 OctSaudia go-live approval, in writingAlbadarneh
Mon 26 OctRelease to productionArpan
Tue 27 OctPublish: gift cards back on sale with OTP. CS briefed. Saudia announcementRahul, Saudia marketing
Tue 3 NovOne-week check: OTP success rate, fraud cases, CS ticketsBrian

Risk: Sender ID. Each day it is late moves every date by one day. Latest publish: Thu 12 Nov.

2 of 10 · OTP & SecurityHigh

Phase 2: OTP at Checkout: publish Wed 9 Dec

Today: BRD with Saudia. Rahul sent 9 questions. Paused on the 13 Oct roadmap, first priority for Abdulelah on 14 Oct.

Sun 18 OctAnswers to the 9 questions (Abdulelah promised them 15 or 16 Oct)Abdulelah, Amr
Wed 21 OctWorkshop with Shahad (Saudia fraud team): account takeover and fraudulent redemptionBrian, Rahul
Tue 27 OctFinal BRD: SMS only, non-Saudi numbers blocked, address lock, fewest clicksBrian
Thu 29 OctSaudia sign-off and CRAlbadarneh
Thu 5 NovOTP step design in checkout, EN and ARRaneen
Thu 5 NovEstimate and ticketsAditya
8 to 26 NovBuildMarketplace engineering
29 Nov to 1 DecInternal QAQA
2 to 3 DecUAT with Saudia, with fraud team scenariosRahul, Saudia
Sun 6 DecSaudia go-live approvalAlbadarneh
Tue 8 DecRelease to productionMarketplace engineering
Wed 9 DecPublish: OTP on at checkout. CS script. Member noticeRahul, Saudia

Risk: Uses the same SMS route as the Gift Card OTP. Needs you to unpause it.

3 of 10 · Future Drops 2026Highest

Overall UI/UX revamp: publish Fri 18 Dec (Saudia date)

Today: Raneen showed home, PLP and mobile on 14 Oct. Saudia wants a new product page and a mobile-first approach.

Thu 15 OctShort brief on the new design for Content Square: the functions agreed on 14 Oct. Abdulelah asked for it to prepare the workshopBrian, Raneen
Sun 18 OctNew product page: specs and description in expandable bars, short mobile pageRaneen
Tue 20 OctContent Square workshop. Abdulelah sends the invite. Show mobile first, no images in advanceAbdulelah, Brian, Raneen
Thu 22 OctConfirm the member Miles balance is available to the storefront ("Shop within your balance", "Chosen for you")Aditya
Thu 29 OctDesign freeze 1: home, PLP, mobile menu. Saudia approvesRaneen, Abdulelah
Thu 5 NovDesign freeze 2: product page, category page, balance sections, "Chosen for you" logicRaneen, Brian
1 to 26 NovFront-end build, web and mobile. Home and PLP from 1 Nov, the rest from 8 NovMarketplace engineering
Thu 26 NovRelaunch banners in two sizes, EN and ARNaif (Saudia marketing)
29 Nov to 1 DecInternal QA on mobile devices, EN and ARQA
2 to 6 DecUAT with SaudiaRahul, Saudia
Mon 7 DecSaudia go-live approvalAlbadarneh
Wed 9 DecRelease to production behind a switch, before the 10 Dec freezeEngineering
Fri 18 DecPublish: switch on for the anniversary relaunch. It can go on 10 Dec if Abdulelah agreesSaudia, Rahul
18 to 24 DecContent Square check on the new pagesBrian

Risk: Largest item. One designer carries it.

4 of 10 · Apple StoreHigh

Apple Store discoverability, mobile view: publish Thu 19 Nov

Today: Bucket 1 (front end only) in progress. Bucket 2 needs a design from Raneen. Legal question on Apple images open.

Thu 15 OctConfirm what bucket 1 has shipped and what is leftRahul
Thu 22 OctLegal answer: can we use Apple marketing imagesAlbadarneh, Saudia legal
Thu 22 OctBucket 2 mobile design, matched to the revamp menu (brand store in the menu)Raneen
Tue 27 OctSaudia approves the designRahul
Thu 29 OctRelease and publish bucket 1Engineering
1 to 12 NovBuild bucket 2Engineering
15 to 17 NovQA and UAT with SaudiaQA, Rahul
Wed 18 NovSaudia go-live approvalAlbadarneh
Thu 19 NovRelease and publish: Apple Store easy to find from the mobile home and menuEngineering, Rahul

Risk: Raneen also carries the revamp. Keep this design small and reuse the revamp menu.

5 of 10 · Product AvailabilityHigh

Coming Soon, Pre-order, Sold Out journey: publish 3 Dec and 10 Dec

Today: Sold Out is live on the Apple Store only. This plan extends it to the whole store. BRD v0.8 (15 Oct) is the latest.

Thu 15 OctDecide product level or variant levelAditya, Akshay
Thu 15 OctBRD v0.8 is the latest (v0.7 already sent). Saudia reviews itBrian
Wed 21 OctEstimate for each modeAditya, Akshay
Thu 22 OctPre-order unit cap and label wordingRaneem Ajana
Thu 29 OctSaudia sign-off and CRAlbadarneh
Thu 29 OctDesign: Notify me button, Coming Soon label, Pre-order badge and checkout (inside the revamp product page)Raneen
Thu 5 NovSaudia approves message templates, EN and AR (Notify me email and SMS, cart message)Heba, Saudia
Thu 12 NovFirst pre-order event product, supplier ship date under 30 daysRahul, partnerships
25 Oct to 19 NovBuild in order: Sold Out store-wide, then Coming Soon (from 1 Nov), then Pre-order (from 8 Nov)Marketplace engineering
22 to 26 NovQA and UAT with SaudiaQA, Rahul
Sun 29 NovSaudia go-live approvalAlbadarneh
Tue 1 DecRelease to production, every mode off by defaultEngineering
Thu 3 DecPublish Coming Soon: Ops switches on the first products. CS briefedOps, Rahul
Thu 10 DecPublish Pre-order with the first event product. Auto refund if not delivered in 28 daysOps, Rahul

Risk: Estimates missing since 8 Oct. Moyasar cannot refund cards after 30 days.

6 of 10 · Future Drops 2026High

Rush Delivery: publish Thu 10 Dec (if go)

Today: No courier or service chosen. Mostly a logistics problem. Rahul did not promise it on 14 Oct.

Thu 22 OctBRD: cities, cut-off time, fee, delivery promiseBrian
Thu 22 OctOps names an owner and lists courier options in Riyadh and JeddahMawi, Wael (Ops)
Thu 5 NovDiscovery done: courier, cost per order, which sellers can hand over the same dayOps
Thu 12 NovGATE: go or no-go with Saudia, fee approved. No-go goes to Abdulelah in writing, moves to 2027Brian, Albadarneh
15 Nov to 2 DecBuild: delivery option at checkout, fee, order routingEngineering
3 to 6 DecQA, UAT and a dry run with the courierQA, Ops
Mon 7 DecSaudia go-live approvalAlbadarneh
Tue 8 DecRelease to productionEngineering
Thu 10 DecPublish in one city firstOps, Rahul

Risk: The service may not exist in the market at a fee Saudia accepts.

7 of 10 · Apple StoreMid

Product Comparison: publish Thu 10 Dec

Today: New. No BRD.

Thu 22 OctCheck Apple product specs are structured fields in the catalogAkshay
Thu 29 OctBRD: compare up to 3 Apple products of the same typeBrian
Thu 5 NovSaudia sign-offRahul
Thu 12 NovDesign, EN and ARRaneen
15 Nov to 2 DecBuildEngineering
3 to 6 DecQA and UATQA, Rahul
Mon 7 DecSaudia go-live approvalAlbadarneh
Tue 8 DecRelease to productionEngineering
Thu 10 DecPublish on the Apple StoreRahul

Risk: If specs are free text, Ops must fill fields for every Apple product first.

8 of 10 · Apple StoreMid

Bundle Products: publish Thu 10 Dec

Today: New. Discussed in the July workshops, no BRD.

Thu 22 OctSaudia lists the first bundles (for example iPhone, case, charger) and the price ruleRahul, Saudia
Thu 29 OctBRD: a bundle is one catalog product, stock equals its lowest part, one price in MilesBrian
Thu 5 NovSaudia sign-offRahul
Thu 12 NovDesign: bundle card and product pageRaneen
15 Nov to 2 DecBuildEngineering
Thu 3 DecOps sets up the first bundlesOps
3 to 6 DecQA and UATQA, Rahul
Mon 7 DecSaudia go-live approvalAlbadarneh
Tue 8 DecRelease to productionEngineering
Thu 10 DecPublish the first bundles on the Apple StoreOps, Rahul

Risk: A real bundle engine does not fit before December. One catalog product per bundle does.

9 of 10 · Apple StoreMid

AppleCare: publish Thu 10 Dec (if a supplier)

Today: Dropped for the July launch. The product page sections are hidden in Figma and can come back.

Thu 22 OctGATE: a supplier can sell AppleCare (codes, price per device, activation). No supplier means 2027Rahul, partnerships
Thu 29 OctBRD: add-on on the product page and in the cart, how the member receives itBrian
Thu 5 NovSaudia sign-off. Design: un-hide the existing Figma sectionsRahul, Raneen
8 to 26 NovBuildEngineering
29 Nov to 3 DecQA and UATQA, Rahul
Sun 6 DecSaudia go-live approvalAlbadarneh
Tue 8 DecRelease to productionEngineering
Thu 10 DecPublish on Apple product pagesRahul

Risk: Depends on a supplier contract, not on engineering.

10 of 10 · Apple StoreMid

Buy Now Pay Later: Tabby: publish Thu 10 Dec (if signed)

Today: No owner, no contract. Three parties: AlFursan, Tabby, Merit. Rahul did not promise it on 14 Oct.

Sun 18 OctTamer names a commercial ownerTamer
Thu 29 OctIntro call with Tabby, draft of the three-way termsTamer
Thu 5 NovBRD: where Tabby shows, Miles plus card split, refundsBrian
Thu 12 NovGATE: terms signed and Tabby merchant account open. Not signed means 2027, in writing to AbdulelahTamer, Albadarneh
15 Nov to 3 DecIntegration and Tabby test sign-offEngineering
6 to 7 DecUAT and Saudia go-live approvalRahul, Albadarneh
Tue 8 DecRelease to productionEngineering
Thu 10 DecPublish at checkout on the Apple StoreRahul

Risk: Past cases spent two months on terms before tech could start.

What can break the plan

Nine builds overlap in November on the Marketplace team

Engineers

Revamp, Checkout OTP, Drop 4, Apple mobile, Rush, Comparison, Bundles, AppleCare and Tabby all build between 25 Oct and 3 Dec, on the Marketplace team outside Jordan. Aditya names an owner per build by Thu 22 Oct.

One designer

Raneen designs the revamp, Apple mobile, Drop 4 screens, Comparison, Bundles and AppleCare. Revamp first, the rest reuse its parts.

Saudia approvals

Sign-offs, CRs, templates and go-live approvals land from 29 Oct to 7 Dec. Each late approval moves its publish date by the same days.

Cut order if capacity is short: AppleCare, then Tabby, then Product Comparison, then Bundle Products. All four are Mid.

Sources: Q4 Drop Plan v0.2, MOM Drop 3/4 Estimates 6 Oct
What you decide

Four decisions, each with a recommendation

1

Unpause Checkout OTP?

Yes. Abdulelah ranks it first. Publish 9 Dec. Promo Codes stay paused (Low).

2

Tell Abdulelah the gates now?

Yes, in writing. AppleCare 22 Oct, Rush and Tabby 12 Nov. A missed gate means 2027.

3

Build owners

Ask Aditya to name one owner per build on the Marketplace team by Thu 22 Oct.

4

Revamp switch-on

Ready 9 Dec behind a switch. Offer Abdulelah 10 Dec. If he wants the anniversary, it goes on 18 Dec.

Recommendations are mine. Nothing is committed with Saudia or engineering.
This week and next

Eight dated actions start every plan

DateActionOwner
Thu 15 OctShort brief on the new design for Content Square: the functions agreed on 14 Oct (Abdulelah asked for it)Brian, Raneen
Thu 15 OctGift Card OTP: is the sender ID letter signed and with Unifonic? Which date does Unifonic activate it?Rahul
Thu 15 OctApple Store mobile: which bucket 1 front-end changes are live, and which are left?Rahul
Thu 15 OctBRD v0.8 (Coming Soon, Pre-order) is the latest. Saudia sign-off due Thu 29 OctBrian, Albadarneh
Sun 18 OctTabby owner named. Answers to the 9 OTP questionsTamer, Abdulelah
Tue 20 OctContent Square workshopAbdulelah, Brian, Raneen
Wed 21 OctShahad workshop on Checkout OTPBrian, Rahul
Thu 22 OctBuild owners from Aditya. Rush BRD. AppleCare supplier gateAditya, Brian, Rahul
None of these is sent or filed yet.
Limits of this plan

What I could not check

Estimates

No engineering estimate exists for any item except the built Gift Card OTP. Build windows are my proposal.

New Apple Store items

Comparison, Bundles and AppleCare have no BRD and no prior scope beyond July notes. Their plans start from zero.

Approvals

Every publish date assumes Saudia approves on the planned day.

The transcript

Garbled around minutes 40 to 60 of the 14 Oct workshop. Re-listen before quoting.

Written plan: Abdulelah_Deliverables_Plan_2026-10-14.md (v0.2)