CANCELLED (as of 2 Nov 2026): Plan A (December), the title idea "the revamp is the migration" and the 18 Dec relaunch as the cutover. The end-December target was closed on 14 Oct. NOT VERIFIED since 14 Oct 2026: whether Plan B (single February switch) is the plan being followed. The current plan is the 28 Oct re-scope. Check with Brian.
Al Fursan migration · 14 Oct 2026 · draft for discussion

Status as of 2 Nov 2026. Sections marked CANCELLED, SUPERSEDED, PAST or NOT VERIFIED are history or unconfirmed. The current migration plan is the re-scope of 28 Oct 2026: build ends mid-January 2027, canary second half of January, switch first week of February 2027.

The revamp is the migration

Two plans to move Al Fursan from the Old World to the New World after Fred's review on 14 Oct: Plan A for December, Plan B as the February fallback. Status on 2 Nov: the build ends mid-January 2027, canary runs in the second half of January, and the latest safe switch is the first week of February, before Ramadan. The February date is at risk at current staffing.

The idea in one sentence

Saudia already wants a new store on 18 Dec. Launch Raneen's new design on the New World, so the migration rides inside the relaunch.

CANCELLED (as of 2 Nov 2026): the migration no longer rides inside the 18 Dec relaunch. NOT VERIFIED since 14 Oct 2026: Saudia's 18 Dec relaunch date.

→ / Spacenext slide ←previous slide Escall slides Ffullscreen Nspeaker notes Tlight or dark
Sources: Fred review 14 Oct, prep session 13 Oct, revamp workshop 14 Oct, Canary Cutover Plan v2.1, Storefront Admin Portal PRD v3.2. NOT VERIFIED since 14 Oct 2026: whether these are the current versions.
SUPERSEDED (as of 2 Nov 2026): card 1 "December target stays" was Fred's ask on 14 Oct. Now the February 2027 hard deadline stands and the end-December target was closed on 14 Oct (re-scope 28 Oct). CANCELLED (as of 2 Nov 2026): the question "smallest store that looks complete on 18 Dec". PAST: Fred's "check-in again in two weeks" (about 28 Oct) has passed. NOT VERIFIED since 14 Oct 2026: card 5 "about 8 developers, max": most of the Tintash team left at the end of October. Check headcount with Brian.
What Fred set today

Keep December, cut the scope, finish by February

1

December target stays

"Kill the scope if you want to secure end of December."

2

Must look complete

Saudia should not see what is missing behind the store.

3

End of Feb is the hard stop

Full completion, "non-negotiable".

✕

No legacy ownership

Old Plan C: "it's not a scenario, it's not happening".

5

About 8 developers, max

No 11 new hires. Check-in again in two weeks.

What this means: the question is no longer "which date". It is "what is the smallest store that looks complete on 18 Dec".

Source: Fred review, 14 Oct 2026, 18:01 WIB (local recording). Update 2 Nov: the December target no longer stands. Fred set the February 2027 hard deadline on 14 Oct (re-scope of 28 Oct).
SUPERSEDED (as of 2 Nov 2026): "170 urgent gap tickets" and "297 dev-days" were the 14 Oct figures. Now Re-scope v0.1 (28 Oct): 117 tickets (102 open Urgent plus 15 epics); P0 must 59 tickets, 155.5 dev-days plus 6 unestimated; must-have dev scope about 187 dev-days. NOT VERIFIED since 14 Oct 2026: the "8 started" count and the 5 developers, check with Brian. The waffle chart stays as history.
Where we start

Only 8 of 170 urgent gap tickets have started

297

dev-days to close the urgent tickets only

5

developers on 14 Oct: 3 Merit plus 2 Tintash. Wshah leads. Update 2 Nov: most of the Tintash team left at the end of October.

End Nov

Zarar Tahir (Tintash) leaves. Most of the Tintash team left at the end of October.

Done or in progress (8)Not started (162)
Source: Albadarneh's slides in the Fred review, 14 Oct. One square is one urgent ticket.
CANCELLED (as of 2 Nov 2026): the December capacity case (297 vs about 200 dev-days to the 10 Dec code freeze). The freeze belonged to Plan A and the end-December target was closed on 14 Oct. SUPERSEDED (as of 2 Nov 2026): was 297 dev-days for 170 tickets, now about 187 dev-days must-have scope, down about 32 percent from about 273 (re-scope 28 Oct). The bar chart shows the 14 Oct view.
The capacity gap

December scope must shrink by at least a third

Capacity is rough: about 40 working days to the 10 Dec code freeze, times 5 developers. No buffer. New joiners not counted.

Update 2 Nov: Re-scope v0.1 (28 Oct, owner Brian) counts 117 tickets (102 open Urgent plus 15 epics). Must-have dev scope is about 187 dev-days, down about 32 percent from about 273. Sources: 297 dev-day estimate from the Fred review; capacity is rough arithmetic, not an engineering estimate
PAST: the "Today" marker (14 Oct) in the timeline has passed. CANCELLED (as of 2 Nov 2026): the "18 Dec relaunch" marker belonged to Plan A. NOT VERIFIED since 14 Oct 2026: Saudia's 18 Dec relaunch date. SUPERSEDED (as of 2 Nov 2026): the early-February stop still holds: latest safe switch is the first week of February 2027, before Ramadan (about 8 Feb). "End of February" stays too late.
The real deadline

Fred's end-February date falls inside Ramadan, so the true stop is early February

Fred: the switch must never land in Ramadan.

Ramadan 2027 starts around 8 Feb. So "end of February" is already too late.

Ramadan dates are approximate (moon sighting). Anniversary date from the revamp workshop with Abdulelah.
Today: the Old World

Everything Al Fursan runs on is legacy

MembersMerit opsand SaudiaMerit ops(catalogue) Legacy storefront Legacy admin portal Legacy ops systemproducts and stock Legacy back endorders, catalogue, Miles,payments (Marketplace team) MGCgift cards Financereports Run by a separate team outside Jordan. Every month we keep it costs a second tech team.
Source: prep session 13 Oct; Old World vs New World map in the repo
CANCELLED (as of 2 Nov 2026): Plan A, the target picture for 18 Dec. The end-December target was closed on 14 Oct. SUPERSEDED (as of 2 Nov 2026): "Drop 4 built once on the New World" was Plan A. Now Drop 3 and Drop 4 are built on the legacy marketplace (decided 6 Oct). API-only sellers will not move to the Seller Portal (28 Oct). NOT VERIFIED since 14 Oct 2026: "Marthino checks reports during canary steps 0 to 2": canary is now the second half of January.
Plan A on 18 Dec

New storefront, copied admin, all on the New World

MembersMerit opsSellers New storefrontRaneen's design Copied admin portallegacy screens, new data Seller Portalnew: sellers self-serve E-Commerce Solutioncore, OMS, payments,Miles MGCas a supplier Financesame records Legacy: warm, no traffic Hover a box for detail. Saudia sees a revamp, not a migration.
New WorldKept or outsideLegacy on standby
CANCELLED (as of 2 Nov 2026): Plan A (ships 18 Dec, builds Drop 4 once). The end-December target was closed on 14 Oct. Plan C was closed on 14 Oct. SUPERSEDED (as of 2 Nov 2026): the swimlane dates are the 14 Oct plan. Now Drop 3 and Drop 4 are built on the legacy marketplace (decided 6 Oct). NOT VERIFIED since 14 Oct 2026: whether Plan B (single February switch, 5 Feb) is being followed. The current plan is the 28 Oct re-scope: canary second half of January, switch first week of February.
Two plans, side by side

Plan A ships in December and builds Drop 4 once; Plan B waits for February

LegacyNew WorldDrop 4 built a second timeSwitch dateRamadan
CANCELLED (as of 2 Nov 2026): the Plan A column ("Yes, 18 Dec", "once on the New World"). The end-December target was closed on 14 Oct. PAST: the switch rule date "by 21 Oct" has passed. NOT VERIFIED since 14 Oct 2026: Wshah's answer on Drop 4 and so the Plan B switch. Check with Ahmad Wshah. SUPERSEDED (as of 2 Nov 2026): Drop 3 and Drop 4 are built on the legacy marketplace (decided 6 Oct).
How the plans score

Plan B is not lighter: it builds Drop 4 twice, with two teams

Switch rule: if Wshah says by 21 Oct that his team cannot build Drop 4 while closing the gaps, we take Plan B.
Ruled out: legacy ownership (Fred closed it) · a look-alike December move · replacing back-end APIs one by one under the old front end (backward-compatibility work nobody designed for) · full scope in December (needs about 11 new developers)

CANCELLED (as of 2 Nov 2026): this Plan A picture, including the 18 Dec relaunch node (end-December target closed on 14 Oct). PAST: "by 21 Oct" has passed. "Before 26 Nov" is superseded: canary is now late January. SUPERSEDED (as of 2 Nov 2026): stream 4: API-only sellers will not move to the Seller Portal (28 Oct). NOT VERIFIED since 14 Oct 2026: the stream owners. Now: Ahmad Wshah (Engineering Lead), Mohammad Albadarneh (Project Manager), Muawiya Shahin (Head of LiveOps), Rana Al Sukhon (Core, PIM, Settlement).
Plan A in detail

Planning comes first, then four streams run in parallel

1 · by 21 OctPlan and scopeAhmad Wshah 2 · Storefront and Drop 4Wshah's team · Raneen's design, browse, pay, track 3 · Copied admin portalWshah · legacy screens, New World data 4 · Sellers to Seller PortalAlbadarneh, Muawiya · before 26 Nov 5 · Money and recordsMarthino with Finance 18 DecRelaunch
Update 2 Nov: API-only sellers will not move to the Seller Portal. The new e-commerce Seller API is not built and joined the migration backlog on 28 Oct. Settlement Service (AFM-14.1) was never planned and has no build owner; Rana Al Sukhon (Senior PM, E-Commerce Solution, joined 1 Nov) proposes an owner by 19 Nov 2026.
SUPERSEDED (as of 2 Nov 2026): "canary step 0 (26 Nov)" was Plan A. Canary is now the second half of January 2027 (28 Oct re-scope). NOT VERIFIED since 14 Oct 2026: the copied-admin gate decision and PRD v3.2 as the current version. The admin backend moved to Thino's squad on 12 Oct.
Workstream 3

Copy every legacy admin screen, re-point it, then sort it into three states

Legacy adminscreens ops knows Data mapold source → New Worldservice, per screen ✓ Worksorders, cancel or reprocess, tax invoice, banners ◐ Works with lessfewer filters, fewer controls ⏸ Under maintenancenever breaks the store or an order

Fred sees the "maintenance" list before canary step 0 (26 Nov). The new Storefront Admin Portal (PRD v3.2) stays the 2027 target.

PAST: "By 23 Oct" has passed. NOT VERIFIED since 14 Oct 2026: whether Marthino gathered the finance requirements and still owns this. Check with Brian. SUPERSEDED (as of 2 Nov 2026): "canary steps 0 to 2" were the December plan. Canary is now the second half of January 2027. Settlement Service (AFM-14.1) was never planned and has no build owner; Rana Al Sukhon proposes one by 19 Nov 2026.
Workstream 5

Marthino gets the finance requirements first, then the New World produces the same records

1

Marthino gets requirements

Most of the data sits in the data warehouse he manages. With Finance, he confirms how an Al Fursan transaction is recorded today. By 23 Oct.

2

Same records

New World produces the same fields, the same period cut, the same totals.

3

Parity check

Marthino puts old and new reports side by side during canary steps 0 to 2.

Records that must match:

Miles redeemedCard amountVATSeller payableSaudia invoicePer-period Miles total
Gap: how Finance records Al Fursan today is not written down anywhere in the repo. That is why step 1 gathers requirements first.
SUPERSEDED (as of 2 Nov 2026): the chart (0 percent on 26 Nov to 100 percent on 22 Dec, 18 Dec relaunch) is the 14 Oct plan. Now: canary second half of January 2027 (team aim about 8 Jan), cutover end of January, latest safe switch first week of February. NOT VERIFIED since 14 Oct 2026: whether Saudia agreed to support a step-by-step rollout, and Canary Cutover Plan v2.1 as the current version. Check with Mohammad Albadarneh.
Release

A step-by-step rollout needs Saudia's support, so Albadarneh must secure it first

Routing members by step depends on Saudia's login and domain. Albadarneh asks Saudia to support it. If they do not, we switch everyone on 18 Dec and keep legacy warm to roll back.

Source: Canary Cutover Plan v2.1, 9 Oct 2026. Update 2 Nov: the 26 Nov to 22 Dec dates are superseded. Canary is now the second half of January (team aim: about 8 Jan), cutover at the end of January, and the latest safe switch is the first week of February.
CANCELLED (as of 2 Nov 2026): this Plan A timeline (build to 10 Dec, relaunch 18 Dec, legacy off in January). The end-December target was closed on 14 Oct. SUPERSEDED (as of 2 Nov 2026): the "Tintash developers leave 30 Nov" bar is wrong: most of the Tintash team left at the end of October 2026, and Zarar Tahir leaves at the end of November. PAST: bars for 15 to 29 Oct have passed. Current plan: build ends mid-January, canary second half of January, switch first week of February (re-scope 28 Oct).
Plan A timeline

Build to 10 Dec, relaunch 18 Dec, clean up in January

CANCELLED (as of 2 Nov 2026): "Keep for 18 Dec" (Plan A; the end-December target was closed on 14 Oct). SUPERSEDED (as of 2 Nov 2026): the current scope split is Re-scope v0.1 (28 Oct): P0 must 59 tickets, 155.5 dev-days plus 6 unestimated; P1 must but slim 13 tickets, 31.5 dev-days; Delay 15 tickets, 67.5 dev-days. NOT VERIFIED since 10 Sep 2026: this keep and leave list and the Ramadan offers page deadline (before about 8 Feb). Check with Brian.
Scope

Keep what a member needs to buy; leave the rest for January on purpose

Keep for 18 Dec

SSO and live Miles balanceHome, list, product pageBasic searchApple Store, gift cardsMiles and Miles plus cardGift card reveal (OTP)Addresses, order historySold out, coming soon, pre-orderOps: orders, banners, collectionsAllow or block membersFloat balanceMaintenance page, kill switch

Leave for January to early February

AI search, recommendationsWishlistsOrder ratingMagic link, no-MFASupport tickets in appFee by card schemePromotions, codesPrice history, audit extrasMember lookup, fraudTenant self-serveAnalytics embed

Check first: Ramadan offers page (due before about 8 Feb) and cashback Phase 1.

Sources: feature inventory vs backlog (10 Sep), Storefront Admin Portal PRD v3.2. Hover a grey chip for the reason.
CANCELLED (as of 2 Nov 2026): "In Plan A all 13 are built on the New World by Wshah's team" (Plan A cancelled). SUPERSEDED (as of 2 Nov 2026): Drop 3 (end Oct) and Drop 4 (end Nov) are built on the legacy marketplace (decided 6 Oct). Rush Delivery goes through the supplier-commitment route, not a Merit warehouse. PAST: the end-Oct date for Drop 3 has passed. NOT VERIFIED since 15 Oct 2026: Saudia's Q4 priority table (13 in Q4, 3 wait). Check with Brian.
Drop 4: the full list from Saudia

16 items; Saudia expects 13 in Q4, only the three lowest wait

Highest (2)

Gift Card OTP flow
OTP and security · legacy first
Overall UI/UX revamp
Future drops

High (6)

OTP at checkout, phase 2
OTP and security
Apple Store discoverability, mobile
Apple Store
Coming Soon
Product availability
Pre-order
Product availability
Sold Out journey
Product availability · done on legacy
Rush Delivery
Future drops

Mid (4)

Product comparison
Apple Store
AppleCare
Apple Store
Bundle products
Apple Store
Tabby (buy now, pay later)
Apple Store

Low (1)

Promo code enhancements
Promo codes

Lowest, after Q4 (3)

Cashback
Apple Store
Notification Hub
Future drops
eSIM
Future drops
Source: Saudia's Q4 priority table, shared by Brian 15 Oct. In Plan A all 13 are built on the New World by Wshah's team. Update 2 Nov: Drop 3 (end Oct) and Drop 4 (end Nov) are built on the legacy marketplace, not on the New World (decided 6 Oct).
SUPERSEDED (as of 2 Nov 2026): this table lists needs on the New World; Drop 3 and Drop 4 are built on the legacy marketplace (decided 6 Oct). Rush Delivery "Needs a partner" is now the supplier-commitment route. PAST: "Wshah sizes these by 21 Oct" has passed. NOT VERIFIED since 14 Oct 2026: the sizing outcome. Check with Ahmad Wshah. CANCELLED (as of 2 Nov 2026): the note "Relaunch 18 Dec" (Plan A).
What each Q4 item needs on the New World

Revamp, OTP and buying modes carry most of the work

ItemPriorityStorefrontBack endAdmin and opsNote
Gift Card OTP flowHighestOTP before the code showsSaudia SMS gatewaynoneLegacy first
Overall UI/UX revampHighestNew home, list, product pageCollections by Miles balanceBanners, collectionsRelaunch 18 Dec
OTP at checkout, phase 2HighOTP step at checkoutSMS gateway, fraud rulesnone
Apple Store discoverabilityHighEntry points, mobile layoutnoneCollections, banners
Coming SoonHighNotify-me button and formSubscriber list, email and SMSMark coming soon
Pre-orderHighPre-order button, termsOMS pre-order, auto refundOpen, close per productUnder 30 days
Sold Out journeyHighLabel, cart messageSold-out flag per productSwitch per productDone on legacy
Rush DeliveryHighDelivery optionOMS and courier partnerFulfilmentNeeds a partner
Product comparisonMidCompare viewComparable attributesAttribute data
AppleCareMidAdd-on offer on deviceAdd-on linked in OMSLink to devices
Bundle productsMidBundle page and priceBundle price, stock, OMS splitCreate bundles
TabbyMidPayment optionPayment integrationFinance settlementNeeds a contract
Promo code enhancementsLowPromo code fieldPromotions serviceCampaign settingsService not live yet
Still being detailed, no estimates yet. Wshah sizes these for the New World by 21 Oct.
PAST: the end-October check-in and the 21 Oct decision date have passed. CANCELLED (as of 2 Nov 2026): decision 1 (Plan A as the proposal) and the 18 Dec switch in decision 4. Plan A and the end-December target were closed on 14 Oct. NOT VERIFIED since 14 Oct 2026: the outcomes of decisions 2, 3 and 4. Check with Ahmad Wshah (2) and Mohammad Albadarneh (4).
Decisions to close

Four calls before the end-October check-in with Fred

1

Plan A is the proposal, Plan B the fallback

For our brainstorm, and for the end-October check-in with Fred.

2

Wshah decides on Drop 4 by 21 Oct

Can his team build Drop 4 on the New World while closing the gaps? Yes: Plan A. No: Plan B, extend to February.

3

Accept a reduced admin portal

Changes Brian's earlier position: the copied admin is the cutover gate, not full parity.

4

Albadarneh gets Saudia's support for the rollout

A step-by-step rollout needs Saudia's help on login and domain. Without it, one switch on 18 Dec.

Update 2 Nov: Saudia (Abdulelah) approved BRD v2.1 on 30 Oct. SAB is out of migration scope, and both e-commerce solutions stay live after the migration. Rush delivery goes through the supplier-commitment route, not a Merit warehouse. Rana Al Sukhon now owns the E-Commerce Core, PIM and Settlement part of the migration; Brian stays the accountable migration lead until the switch. Limits: transcript is from the local recorder and partly garbled; capacity is rough; the 170-ticket list was not read line by line; Drop 4 details are still in progress.