Al Fursan · Merit internal · v2.1 · 16 October 2026

Q4 for fewer complaints. New features in Q1, built once.

Drop 4 for Thamer Bamieh, Raouf Cherkawi and Wael Helal. We need your help with Saudia.

→ Space next ← back Esc grid F fullscreen N notes T light or dark
This is internal. Nothing goes to Saudia until you agree. The deck is about Saudia's members first: what hurt them in September, and what Q4 fixes. Merit's capacity comes later, and only once.
The ask

We ask you for four things

1

Agree the cut and take it to Saudia before the end of October.

2

No build before a signed CR and agreed commercials. This protects both sides.

3

From 1 November, new requests go to the Q1 plan on the new platform.

4

Wael: Q4 goes to fewer complaints and fewer cancellations, with the fixes on slide 9.

State the four asks and stop. The rest of the deck is the reason for each ask. Ask 4 is now concrete: slide 9 lists the Q4 fixes and what each one removes.
The short version

Most of the hold is already true

1

Half the Drop 4 list waits on a contract, a supplier or a Saudia decision. We write that down now, so nobody promises dates that Merit does not control.

2

Saudia members feel September today. Complaints and cancellations went up. Q4 fixes that.

3

The new features ship in Q1, once, on a platform that runs them properly, and the switch stays before Ramadan.

This is the slide to repeat to Saudia. We are not cutting Saudia's list. We write down what the calendar already decided, we fix what members complain about, and we ship the new features once.
Reason 1 · What September taught us

The last rushed launch on legacy still hurts members

248
Apple orders by 1 Oct, against 113 secured units
147
orders still pending on 12 Oct
61
orders moved to another supplier by hand, 9 to 10 Oct
46
orders missing from the API while still in OMS, 8 Oct
"remove all out-of-stock products from the marketplace to avoid receiving new orders for unavailable items"Wael, about 10 October
The 28 August incident: miles were deducted twice from a member, and both cases came back as complaints. The per-call refund limit from that RCA was still not built on 9 October.
Every new feature on legacy in Q4 is another chance to repeat September.
Apple Store went live about 6 September on a placeholder supplier with no stock. By 1 October there were 248 orders against 113 secured units, and 147 were still pending on 12 October. Ops moved 45 orders and then 16 more by hand. 46 orders disappeared from the Merchandise API. Wael asked to take out-of-stock products down. Do not call legacy buggy: Jira has only 7 Saudia bugs since July. The point is operational load, not defects. Sources: Apple Store RCA 13 Oct; #saudia-tech-ops-; #apple-store-iphone18-stock; #tmp-saudia-cyber-incident-28aug2026.
Reason 2 · Julie's Q4 goal

Julie's Q4 bar: fewer cancellations and complaints

Care cases per 1,000 orders, Al Fursan store (orders placed in the month)
Jul
Aug
Sep
Oct 1-14
Julie, 6 OctOctober cancellations must be below September. "Delays and cancellations are not acceptable."
23% → 16%Cancellations, Aug to Sep. Ops expects October to rise: Apple orders come in before stock.
41 → 83"Where is my order" cases per 1,000 orders, September to October.
The dashboard shows 82.6: it divides by three months of fulfilled orders. September orders alone give 175.
This is not Product's preference. Julie set it in the Marketplace review on 6 October: October cancellations below September, fulfilment towards 2 to 5 days, penalties for late suppliers, and a plan to bring care cases to 50 or fewer per 1,000 orders. Julie did not rank these against named features; that ranking came from the internal Drop 3 and 4 meeting the same day, so do not attribute it to her. Wael's team carries the load. The numbers come from Metabase, read 15 October: 10,579 cases from the Al Fursan customer care project. October is 1 to 14 October, so treat it as direction. 159 merchandise orders were older than 10 days on 14 October. Do not quote 82.6 against 175 in front of Saudia without the metric note.
Reason 3 · The calendar already decided

Half the list is blocked outside engineering

ItemWaits onWhere it stands
Rush DeliverySaudia funding, new Ops flowQ1, "subject to Saudia's dedicated funding and operational readiness". New courier steps for Ops while 269 orders are still open
Tabby (BNPL)Three-way dealWorkshop 14 Oct: about two months before tech can start
AppleCareA supplierNone yet. Decision 22 Oct
OTP at CheckoutSaudia: the goalPaused 12 Oct. BRD review: nine comments open
Promo codeDiscount fundingBuilt. Ships switched off until the CR is signed
CashbackSaudia: the ruleBuilt by payment type. Scope moved to by category. On hold
Merit's own workshop summary of 14 Oct already says Rush Delivery and Tabby "depend on external parties".
This is the answer to Raouf's commitment of 23 September that these were the last initiatives for 2026. The commitment is not broken by Merit: most of the list is blocked outside engineering. Frame the CR rule as protection for both sides, not as blame. Thamer owns the promo funding talk.
Reason 4 · Built twice

The migration uses almost all our capacity to January, and Drop 4 is not in it

Developer-days from now to the 28 January switch

Drop 4 on legacy takes all of what is left. Then each feature is built again on the new storefront.

"Migration Backlog list not including Drop 4 ... adding Drop 4 will have a significant increasing in the scope."Wshah, 13 October
Only if hiring landsThe 375 needs 5 new developers from 15 November. If they start 1 December, the left over is about 55. With 2 hires, about 0. On 1 October, 1 of 3 open roles was filled.
Estimates are rough. Wshah's ticket-by-ticket estimate lands on Sunday 18 October.
Read the bars top down: what the team can do to 28 January, what the migration needs, what is left, and what Drop 4 on legacy would take. The capacity comes from the migration plan of 15 October, after 20% for review and test. The Drop 4 figure of about 80 is the rough estimate from the alignment doc; Wshah confirms on 18 October. Use this reason once, after the Saudia reasons. Fred on 1 October: "out of three i only got one".
Reason 5 · The dates

Ramadan sets the deadline, and the legacy builders leave on 30 November

Nov 2026 Dec Jan 2027 Feb 30 Nov Tintash leaves 10 Dec code freeze About 8 Jan canary 28 Jan to 4 Feb switch, last day Ramadan About 8 Feb

If the switch slips, the next window is after Eid: late March or April, with 2 to 3 more months on two platforms and two admin portals for Saudia Ops.

Ramadan date is an estimate. Confirm locally. Fred, 14 Oct: no switch in Ramadan, because users notice.
The Tintash developers who build Drop 3 and Drop 4 on legacy leave on 30 November. Features they ship late in November reach the 10 December freeze with nobody left who built them. Holding Drop 4 keeps the Ramadan date. Building all of it pushes the switch into Ramadan or after Eid, which is Saudia's peak season.
What Q4 delivers instead

Q4 engineering goes to the causes of the complaints

Clear the late orders269 orders open on 14 Oct, 159 older than 10 days. Clear by 31 Oct, then automatic delay messages. Proposed
Suppliers held to 2 to 5 daysFulfilment SLA per supplier, penalties for late suppliers. Decided, Julie 6 Oct
Stock drops on every order, every supplierSold-out items hide or switch to pre-order, so members cannot buy missing stock. Approved, Wael 13 Oct
Gift card: tell members when the card is readyThe "being prepared" message is live (MP-11714). Next: "order received" and "card ready" notifications through Saudia's Notification Hub. Proposed, needs Saudia
Fix login and miles displayThird-largest reason, 40 per 1,000 orders. Root cause by 31 Oct, fix in November. Proposed
Refund limit per callOpen item 4 from the August incident RCA, which stops a repeat of double-deducted miles. Open since Aug
Each item answers a top complaint reason or a decision Julie made on 6 October.
The proposed items come from the care-case analysis of 15 October; nobody has agreed to own them yet. The gift card hold is a 24-hour fraud-review window for Saudia and Ops, live for all gift card orders. The storefront "being prepared" message already shipped (MP-11714, Done), and "where is my code" is still 60 per 1,000 orders in September. So the next step is the Phase 2 notifications in the Delayed Gift Card BRD, which go through Saudia's design approval and Accenture. Never show security or review wording to members. A shorter hold is Saudia and Ops' call, not ours. Stock decrement for all suppliers was approved by Wael on 13 October.
Two paths

Limit Q4: fewer complaints, switch on time. Else: pay twice, slip

If we limit Q4 to the highest items

What happens
4 highest items ship in 2026
Q4 engineering goes to the complaint fixes
Switch 28 January, before Ramadan
Migration margin stays for the switch
The rest ships in Q1, built once

Else: we build all of Drop 4 on legacy

Complaint fixes wait while new features shipMembers, CS
Switch slips to after Eid (late March or April)Leadership, Saudia
Each feature built on legacy, then againMargin, cost
Two platforms, two admin portals2 to 3 more months
Features shipped by a team that leaves 30 NovSupport risk
This is the decision in one slide. Ask them which path they want to defend with Saudia.
The proposal

Four items in 2026, the revamp in January, the rest in Q1

2026

Saudia priority shown
Gift Card OTP Highest
OTP at Checkout, once Saudia sets the goal High
Coming Soon, Pre-Order, Sold Out High
Apple Store discoverability, bucket 1 High

Early January

With the new storefront
UI/UX revamp Highest

Q1 2027

On the new platform
Apple Store discoverability, bucket 2 High
Rush Delivery High
Product Comparison Mid
Bundle Products Mid
AppleCare Mid
Tabby (BNPL) Mid
Every item, 2026 or Q1, still needs a signed CR before build. Sold Out, Coming Soon and Pre-Order stay: they cut cancellations.
Based on Saudia's priorities of 14 October. Drop 4 core stays: Sold Out, Coming Soon and Pre-Order also reduce cancellations, so they serve the Q4 goal. Wshah confirms effort on Sunday 18 October.
Open decisions

Three decisions are still open

1. Revamp date (the hardest one)

Saudia wants 18 December, the store anniversary. We propose early January, with the canary. On 14 October Merit said "it will try, with no promise yet".

Raouf: does Saudia accept early January?

2. Framing to Saudia

The canary plan says "system upgrade, new servers", not "migration".

Proposal: "Q4 is for fewer complaints and a stable store; the new features land in Q1."

3. Who tells Saudia, and when

Proposal: Raouf with Albadarneh, before the end of October.

Keep the revamp date separate from the easy cuts. Avoid the word migration with Saudia.
Appendix

Sources and version history

VersionDateChange
v1.015 Oct 2026First deck: capacity-first argument, seven reasons, the cut.
v2.015 Oct 2026Saudia-first rewrite: five reasons with evidence, real care-case rate (175, not 82.6), what Q4 delivers instead, sources slide. Removed the defect angle and the 185 and 190 developer-day bars.
v2.116 Oct 2026From Brian's comments: Julie's goals quoted from the 6 Oct review (no ranking claim); Rush Delivery framed as new Ops load; capacity slide redrawn as available, needed, left over; Q4 slide rebuilt from decided and proposed items, gift card fix corrected (message already live, next step is Saudia notifications).

Sources: Apple Store RCA 13 Oct; Customer care cases by reason 15 Oct (Metabase); MOM Marketplace review 6 Oct; MOM Drop 3 and 4 estimates 6 Oct; Delayed Gift Card BRD and MP-11714; Migration plan 15 Oct; MOM migration update 14 Oct; Deliverables plan v0.3; Slack #saudia-tech-ops-, #apple-store-iphone18-stock, #saudia-alfursan-eshop-project, group DM 13 Oct; Fred biweekly transcript 1 Oct. Evidence file: journal/drafts/alfursan_drop4_why_hold_evidence_2026-10-15.md.

Skip this slide when presenting.